KHS Admin Relocation Project

April 2025

KHS Admin Relocation Project April 2025
KHS AdminRelocation ProjectApril 2025

Project Updates - April 2025 Project Updates - April 2025

zoom_out_map

Construction Activity

  • Splicing, disconnecting, and reconnecting to fiber line in new MDF Room.
  • Electrical and Architectural punch walk, and clean up site
  • Closeout documents

Construction Work Planned for this Month

  • Reviewing closeout documents
  • Issuing completion notice
  • NEXT STEP: Starting the demolition project

Celebration of the 100 / 200 Building Celebration of the 100 / 200 Building

Thank you for all who came out to the event! We appreciate the participation and Don Gosney for the photo of the participants on the grand stair.

zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.



Sign up here: bit.ly/CBOCWCCUSD23

Project Website
zoom_out_map

Connecting existing buildings IDF

zoom_out_map
zoom_out_map

Removing Soil Stockpiles

KHS Project Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close
Powered by