Bond Update

February 5, 2026 Bond Update
February 5, 2026Bond Update

COMPLETED! 🏁 COMPLETED! 🏁

User uploaded image
zoom_out_map Show in original size

βœ…Bid Pack 1A - Stadium Phase 1

  • New Turf
  • New Track Surface
  • New Scoreboard
  • New facia on lower home bleachers
  • New perimeter sidewalks and concrete
  • New fencing
  • New Stormwater Management


Budget: $6,667,266

Project Cost: $5,793,286


BP1A contingency balance sheet below:

User uploaded image
zoom_out_map Show in original size

🚨Take Note!🚨 🚨Take Note!🚨

User uploaded image
zoom_out_map

Stadium Work, Phase 2 Summer 2026

It is important to note that the stadium will be renovated in multiple phases. Phase two, scheduled to begin in the Summer of 2026, will include the addition of a new sound system, as well as the completion of the home bleacher facing (top portion).

Stadium Work, Phase 3

Phase three will include the construction of a new entryway and concession on the south end of the current stadium, as well as cosmetic improvements to the current entryway on the North side of the stadium.

It's Tech, Technically! More Upgrades! πŸ’» It's Tech, Technically! More Upgrades! πŸ’»

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

Projecting the very best! πŸ”†

As part of Mattawan Consolidated School’s bond program, we’re making technology improvements that help keep learning running smoothly and safely across the district. First, we’re upgrading backup power units in the network closets that house our school’s critical connectivity equipment. These units help prevent sudden shutdowns during brief power flickers and protect equipment from damage, reducing interruptions to internet access, Wi-Fi, phone service, and the digital tools students and staff rely on every day.

We’re also upgrading our internet security system and adding a second backup unit. This helps protect student and staff information and improves reliabilityβ€”if one unit has an issue, the other can help keep services running.



Finally, we’re replacing 247 classroom interactive projectors across the district with new Epson 770Fi models. Staying with the same vendor helps us save time and money by reusing existing mounts and interactive touch components, while ensuring classrooms have dependable tools that support engaging instruction. Installation will take place primarily over the summer, but we’ll also take advantage of upcoming school breaks to reduce disruption during the school day.

ON-GOING PROJECTS πŸ“† ON-GOING PROJECTS πŸ“†

BID PACKAGE 2A - MAINTENANCE & TRANSPORTATION BID PACKAGE 2A - MAINTENANCE & TRANSPORTATION

User uploaded image
zoom_out_map Show in original size

Its Starts with a Firm Foundation! πŸ’πŸ”¨

Foundations are being poured this week on the new 24,000 square foot maintenance and transportation facility! Permits are in, and the crews are busy fighting the frigid temps and wind chill to press forward with this amazing, important project!


Review all the details below!

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

Bid Package 2A - Site Work & Prep πŸ’πŸšπŸ”§

Did you know?

  • Current Maintenance Building will be demolished to make room for Natatorium/Field House

  • Current Bus Barn will be maintained as a district storage facility

  • New building will serve as primary hub for both maintenance and transportation departments

  • Total Square Footage of new building: 24,554 sq ft

  • Building Highlights:

    • 4 drive through bus maintenance bays

    • Dedicated parts room, wood shop and machine shop

    • Dedicated, dehumidified district storage

    • Locker rooms

    • Kitchen

    • Training room/lounge

    • 4 offices with additional workstations for secretaries and maintenance staff

    • Building Receiving Loading Dock

    • 40 exterior bus parking spots

    • Secured employee parking

    • Exterior salt storage


Check list

βœ… Structure steel has arrived.

βœ… Site prep underway.

βœ… Site clearing is complete.

βœ… On Oct. 13, the Board of Education approved additional site and concrete workβ€”construction work, including site grading, will begin this week or next.

βœ… The Design Team is reviewing the full bid scope of this project and will bring remaining items, including a Guaranteed Maximum Price (GMP), to the November board meeting.


General Information

Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker-and-shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.


This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.


Tree Removal/Replacement & Disc Golf Course

The disc golf course on the west side of the high school was recently removed to prepare for construction of the new transportation and maintenance facility, slated to begin this winter. Approximately nine baskets and several trees were removed, a step the district did not take lightly. We recognize how meaningful this wooded space and recreational area have been for students and neighbors, and we share the disappointment that comes with altering a natural setting. Our team is working carefully to limit environmental impact and is committed to thoughtful tree replacement as part of the project. We are also exploring possibilities for relocating the disc golf courseβ€”potentially off campusβ€”so the community can continue to enjoy the game in a new setting.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

BID PACKAGE 1B - Traffic Flow Relief on the Way! 🚌🚦🚸 BID PACKAGE 1B - Traffic Flow Relief on the Way! 🚌🚦🚸

Great News! Project is Under Budget! πŸ’ΈπŸ’ΈπŸ“ˆ

Bid Package 1B (Traffic Flow) was recently released for bid. The project carried an overall budget of $6.2 million, with the selected bid coming in approximately $200,000 under budget at $5.9 million. The work will be completed in two phases: Phase 1 will begin and be completed during the summer of 2026, with Phase 2 scheduled for the summer of 2027.


Check out the details below!

User uploaded image
zoom_out_map Show in original size

Campus Traffic Flow Design is COMPLETEβœ…

Considerable planning has been accomplished in the redesign of the traffic flow in and around the middle and high school buildings. Based on observation and feedback, we feel we have the best plan possible to address safety and flow concerns. A few notables:


  • Fully separate buses from carpool and staff traffic at both the middle and high schools
  • Reconfigure the carpool traffic routes at both the middle and high schools
  • Add needed parking in front of middle and high schools
  • Add a through drive east to west for bus traffic to move within our district
  • Open Holler Lane to all traffic coming in or out of the campus allowing for efficient flow
  • NOTE: the removal of 4 current tennis courts will be needed to facilitate the bus lane behind the building due to grade and utilities limitations. As a reminder, 12 new courts will be constructed south of the stadium in bid package 4.


Above: concept design of bus loading lanes on the south side of the middle and high schools.

Below: concept design of parking and carpool lanes on the north side of middle and high schools.

User uploaded image
zoom_out_map Show in original size

Classroom Furniture UpdateπŸͺ‘πŸ« Classroom Furniture UpdateπŸͺ‘πŸ«

Installation set for Summer of 26! πŸͺ‘πŸ«πŸŽ

During the summer of 2026, Mattawan Consolidated School will partner with Great Lakes Furniture Supply to install new furniture in both the middle school and high school. Updates will include new teacher workstations at both buildings and select supporting furniture at each building, including choir risers and chairs, music stands, robotics/STEM workstations. Additionally the high school will be receiving a substantial amount of new student classroom furniture. This project was completed under budget, enabling building leaders to secure all items identified as high priorities while enhancing learning and instructional environments districtwide.


Below are various samples of furniture.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

BID PACKAGE 3 - Middle School Cafeteria/Offices BID PACKAGE 3 - Middle School Cafeteria/Offices

User uploaded image
zoom_out_map Show in original size

Schematic Design

Update on Progress

We moved from Schematic Design (last update) to Design development. Schematic design phase develops the 'big ideas' and gets them on paper, "what are we building and does it roughly fit together." Design Development turns the approved conceptual elements in a coordinated, buildable design.


Archived Information on this Project

The middle school project is currently in the schematic design phase. Many broad design elements are coming together and still very fluid and not permanent at this time.


During the pre-bond discussion, there was talk about the construction of a new cafeteria. After much research and study of the current floorplan and needs within the middle school, an exciting, new concept is emerging: renovating and expanding the current cafeteria and the construction of a new main office.


Cafeteria Improvements

The updated cafeteria design focuses on improving student experience, operational efficiency, and community use. Key benefits include:

  • Expanded seating capacity for approximately 400 students, allowing for more flexible scheduling and improved comfort.

  • Dedicated serving and preparation spaces, improving meal service flow and overall functionality.

  • Centralized location adjacent to the main office to enhance safety and supervision during the school day.

  • Proximity to the front of the building, providing convenient access for after-hours and community events.


Main Office Relocation and Redesign

The new main office layout strengthens security, improves daily workflow, and better serves students and families. The redesign includes:

  • More efficient staff workflow through a centralized, connected layout.

  • Integration of β€œThe Den” and student resource areas directly within the office suite for easier access and support.

  • Improved health room design to provide enhanced privacy, accessibility, and student care.

  • Consolidation of essential servicesβ€”placing all administrative and student support functions in one area rather than two.

  • Dedicated receiving area to streamline deliveries for operations and food service, reducing congestion and improving building safety.

Summary

This design revision supports the district’s goals of maximizing existing resources, enhancing safety and efficiency, and improving both student and community experiences. By renovating and expanding the current spaces, the district achieves a more functional, secure, and cost-effective solution that supports long-term operational excellence.


Note below: green shading is the proposed new cafeteria footprint; blue is the new main office construction; purple is the current students' services office. The stand-alone area is 'The Den.'

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

BID PACKAGE 4 - Aquatic Center/Field House BID PACKAGE 4 - Aquatic Center/Field House

Moving into Design Development Phase!🌊🏊

This project involves construction of a new 80,000+ sq/ft natatorium and athletic fieldhouse that will serve as a year-round hub for student athletics and community use. Designed as a standalone facility within the existing athletic complex, it will support swimming, indoor training, and outdoor sports while providing improved access, parking, and connectivity to nearby fields, courts, and the stadium.


The facility will include a competition pool with spectator seating, locker and changing rooms, and spaces for school. The fieldhouse will house a multi-sport turf field, training areas, and support spaces that enhance both athletic performance and event use. Additional amenities will support stadium events and broader athletic programming.


Architecturally, the building is intended to have a strong, welcoming identity that complements existing facilities, featuring transparent elements, durable materials, and prominent district branding. An adjacent athletic entry plaza will serve as a ceremonial arrival space and community gathering area.

ARCHIVED INFORMATION ARCHIVED INFORMATION

Construction Bid Packages Explained Construction Bid Packages Explained

User uploaded image
zoom_out_map Show in original size

Our Plan. Our Students. Our Future. Our Plan. Our Students. Our Future.

User uploaded image
zoom_out_map

Construction Bid Packages Explained

The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.


2024

  • Summer 2024

    • βœ…Owner Direct – Replace Existing Soccer Lights

    • βœ…Owner Direct – Technology Infrastructure (Switches, Wireless, HS Fiber Upgrades)

  • Fall 2024

    • βœ…Owner Direct – Student Device Replacement Phase 1


Winter 2025

  • Owner Direct – Student Device Replacement Phase 2


2025

  • March – August 2025

    • ALMOST COMPLETE - Bid Package 1A – Football Stadium: Inner Scope

  • Summer 2025

    • UNDERWAY - Bid Package 1C – Baseball & Softball Field Improvements

    • βœ…Bid Package 1D – HS Replace Fire Alarm System

    • βœ…Bid Package 1E – HS Carpet Replacement

  • Fall 2025

    • DESIGN PHASE - Bid Package 1F – HS Gymnasium Cooling

    • βœ…Owner Direct – Auditorium (Band Shell, Pit Section, Lighting, Stage Floor, A/V, Curtain)

  • Nov 2025 – Oct 2026

    • UNDERWAY! Bid Package 2 – Transportation & Maintenance Facility


2026

  • March – September 2026

    • βœ…DESIGN PHASE - Bid Package 1B – Campus Traffic Flow

    • βœ…Bids for work

  • Sept 2026 – March 2028

    • DESIGN PHASE - Bid Package 4 – Field House

    • DESIGN PHASE - Bid Package 4 – Natatorium

  • Owner Direct – Replace CR Furniture: Summer 2026


2027

  • Summer 2027

    • Bid Package 3 – MS Upgrade Domestic Water Heaters

    • Bid Package 3 – MS Replace Fire Alarm System

    • Bid Package 3 – MS Replace Building Temperature Controls

    • Bid Package 3 – MS Replace Chiller & Associated Pumps

    • Bid Package 3 – MS Replace Boiler & Associated Pumps

    • Bid Package 3 – MS Add 3rd Boiler for Redundancy

    • Bid Package 3 – MS Classroom Wing Security Doors

    • Bid Package 6 – Upgrade Domestic Water Heaters

    • Bid Package 6 – Upgrade ECEC Gym AHUs to Include Cooling

  • March – August 2027

    • Bid Package 4 – Tennis Court Facility

  • June 2026 – August 2027 (overlapping start)

    • DESIGN PHASE - Bid Package 3 – MS Cafeteria Renovation

  • Sept 2027 – March 2028

    • Bid Package 6 – HS Weight Room Addition


2028

  • March – August 2028

    • Bid Package 6 – HS Locker Room Renovation

  • June 2026 – August 2028 (overlapping start)

    • DESIGN PHASE - Bid Package 3 – MS Front Office Expansion

  • Summer 2028

    • Bid Package 1B – Stadium Press Box Upgrades

    • Bid Package 5 – MS Replace Interior Lighting to LED

    • Bid Package 5 – MS Replace Ceiling Tiles (with Lighting Replacement)

    • Bid Package 5 – MS Replace Corridor Lockers

    • Bid Package 5 – MS Renovate Science Labs (6th & 7th Grade)

    • Bid Package 5 – MS Renovate Toilet Rooms

    • Bid Package 6 – HS Auditorium Exterior Upgrades

    • Bid Package 6 – HS Exterior Masonry Upgrades (@Entry Canopies)

    • Bid Package 6 – HS Replace Interior Lighting to LED

    • Bid Package 6 – HS Renovate Toilet Rooms

    • Bid Package 6 – HS Renovate Science Labs

    • Bid Package 6 – HS Replace Building Temperature Controls

    • Bid Package 7 – Practice Fields

    • Bid Package 7 – Baseball & Softball Upgrades

  • March – August 2028

    • Bid Package 4 – Multipurpose/Soccer Competition Field


TBD

  • Owner Direct – Replace Security Cameras

  • Owner Direct – Technology District Wide: Classroom Upgrades

  • Owner Direct – Technology District Wide: Large Spaces (Gymnasium A/V)

  • Bid Package 7 – Football Stadium: Outer Scope / Entry

  • Additional bus purchasing

User uploaded image
zoom_out_map

Our focus revolves around five key objectives for the bond:


  1. Preserve existing assets
  2. Prioritize safety and security
  3. Provide future-focused academic and extracurricular experiences for our students
  4. Enhance infrastructure
  5. Demonstrate fiscal responsibility


Safety & Security:

  • Addressing traffic congestion, lack of parking spaces, and separation of traffic and busing through enhancements
  • Replacement of outdated, unreliable security equipment at each building

Transportation:

  • Continued replacement of an aging bus fleet

Academic Learning Spaces + Experience:

  • Replacement of original, aged classroom equipment and furniture at middle and high schools
  • Updates to original, outdated science areas at middle and high schools (excluding the newly renovated portions) to ensure students have state of the art experiences.

Fine Arts:

  • Upgrades to lighting and media equipment at the high school auditorium

Infrastructure:

  • Replacement of original, outdated lockers, bathrooms, various ceilings, and lighting at middle and high schools
  • Renovations to high school weight room including expansion to address overcrowding and scheduling issues for student-athletes and physical education courses
  • Upgrade of aged building controls at middle and high schools (water, fire, HVAC, etc.) to provide the most efficient and safe environmental controls
  • Addition of cooling to main gymnasiums at the high school

Student Athletic Experience:

  • Renovation of aged high school locker rooms
  • Renovation of the high school stadium, including artificial turf, new entryways, expanded concessions
  • New high school track - the current track is backwards and nearly unusable in the current condition
  • Upgrades to baseball and softball fields
  • Construction of a new multi-use turf field (soccer, lacrosse, football)
  • Maintenance of existing practice fields; addition of a new outdoor practice space

Other Construction:

  • Addressing overcrowding in the current Middle School cafeteria
  • Replacement of aged, quickly deteriorating tennis courts
  • Replacement of aged transportation building and maintenance building
  • Construction of a fieldhouse facility for indoor practice teams/band to address lack of 12-month practice space; available for community use
  • Construction of a student/community pool
User uploaded image
zoom_out_map Show in original size

Additional Information at your Fingertips Additional Information at your Fingertips

User uploaded image
zoom_out_map

Supporting Docments

Click on the buttons below to review salient information

Bond 2024 Website
General Bond 2024 Information
User uploaded image
zoom_out_map

Construction

User uploaded image
zoom_out_map

Architect

User uploaded image
zoom_out_map

Owner's Representative

Mattawan Consolidated School
R. Fleenor is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter