Avondale Bond Project Progress

Avondale School District is excited to share progress following our December bond update. Since receiving the first round of bond funding in February, we’ve begun investing in several key projects from our 2024 Bond plan. One of our major focus areas has been the Early Childhood Center, where our planning committee has made great strides.


In addition, we’ve started making impactful district-wide upgrades, including:

  • Replacing aging printers and copiers

  • Implementing a hosted faxing solution

  • Deploying PaperCut software to promote secure, eco-friendly printing

  • Replacing buses at end of service life

  • Upgrades to Avondale Learning Center

  • Beginning enhancements to schools, theatre, and field house


Additional details and more information about specific projects and timelines can be found below. We remain committed to transparency and collaboration throughout the bond process. Quarterly updates—including tentative timelines and committee opportunities—will continue to be shared with staff and families and posted at avondaleschools.org/bond.

Upcoming & Ongoing Projects Upcoming & Ongoing Projects

Transportation Purchases:

We’re excited to share that we’ve purchased half a new fleet of buses —a much-needed update as many of our older buses neared the end of their service life. These new buses not only reduce repair costs but also come equipped with enhanced features for driver support and student safety, including improved seat belts designed especially for our youngest riders.

zoom_out_map
zoom_out_map
zoom_out_map

Tech Upgrades:

Scheduled for Summer 2025 & 2026, these technology and infrastructure upgrades will support long-term sustainability and enhanced learning environments:


  • Wired & Wireless Network Refresh

  • UPS (Uninterruptible Power Supply) Refresh

  • Security upgrades: Cameras, access systems, and surveillance software

  • Classroom enhancements: New A/V systems, projectors, teacher devices

  • Building improvements: Upgraded clock systems, phone servers, and firewall/filtering

  • Scoreboard & sound upgrades at AHS and AMS

  • Mobile device management for tablets

Other Projects & Purchases in Motion:

  • New School Busses - Series 1 & Series 2

    • 11 - February 2025 Purchase

    • Additional purchases to come in September 2025 & 2026


  • Avondale Field House Generators - Series 1

    • September 2025 Completion


  • Enhance AHS Performing Arts Center - Series 1

    • September 2025 Completion


  • Enhancing Woodland - Series 1

    • New Chillers and Unit Ventilators at Woodland, New Ceilings, Classroom Casework, Flooring, Roofing Infrastructure

    • Design 4/2025, Bid 6/2025, September 2026 Completion

Avondale Learning Center Avondale Learning Center

zoom_out_map

Upcoming Projects & Final Phases

The Avondale Learning Center, new home to Avondale's Adult Transition Program and Services (ATPS- previously SKILL) and the Avondale RoboJackets opened for the 2024-25 school year. The building has been fully renovated and continues to be updated with help from the recently approved 2024 bond proposal.


Phase 1 of the project has been completed, ending with a privacy fence being added around the parking lot. Phase 2 construction will begin in June 2025 and includes the renovation of a fully equipped PAES lab for ATPS students, along with an upgraded kitchen and cafeteria space. Phase 3, which focuses on the expansion of the Learning Center, is currently in the design phase. This phase will add a new Physical Education Center. Below is an estimated timeline for those projects.


Proposed Estimated Timelines

Phase 2

  • Area 1: Start April/May 2025, End December 2025
  • Area 2: Start June 2025, End August 2025

Phase 3

  • Start April/May 2025, End December 2025

Phase 4

  • June 2026 - August 2026


Interior & Exterior Design Concepts:

zoom_out_map
zoom_out_map
zoom_out_map
Avondale Learning Center Full Construction Schedule Timeline

Early Childhood Center Early Childhood Center

Design Concepts & Timelines

After several meetings, the Early Childhood Center (ECC) Committee has developed strong initial design concepts and will now shift focus to the functionality of interior spaces, playgrounds, and observation areas—all aimed at creating a nurturing and enriching environment for our youngest learners.


Proposed Estimated Timelines:

  • Design
    Start July 2024, End October 2025
  • Out For Bid
    Start November 2025, End December 2025
  • Construction
    Start May 2026, End December 2027


Design Concepts:

zoom_out_map

1/6/2025 Site Diagram

zoom_out_map

After First Community Engagement Event

Updates to diagram: Additional breakout space on eastside of 6 classroom cluster, large motor room and kitchen moved to north wing, receiving/storage on west side
zoom_out_map

After Second Community Engagement Event

Updates to diagram: 2 clusters of 8 classrooms with a Central Commons area

R. Grant Graham Elementary Additions & Improvements R. Grant Graham Elementary Additions & Improvements

Proposed Estimated Timelines & Concepts

  • Design
    Start December 2024, End June 2025
  • Out For Bid
    Start July 2025, End September 2025
  • Construction
    Start June 2026, End August 2027

zoom_out_map

Additional Location Option 1

zoom_out_map

Additional Location Option 2

zoom_out_map

Floor Plan

Next Steps... Next Steps...

Get Involved

Avondale invites our staff, students, families, and community members to actively participate in the planning and implementation of the approved bond projects. With the first round of funding secured and projects entering the design and bidding stages, the district has formed planning committees to collaboratively define the specific details and requirements for each project.


If you are interested in providing input and feedback for the upcoming projects listed below, please click the link to sign up. Your involvement will play a key role in shaping the future of our schools!


Planning Committees Currently Forming

  • R. Grant Graham Elementary Classroom Additions
  • Avondale Learning Center - Phases 2-4


Please Note: Interested members will be contacted on a first come, first served basis. Committees will consist of district administrators, staff, and up to 10 committee members, including students, families, and community members.


Upcoming Committee Meetings:

  • May 6, 2025: Avondale Early Learning Center Committee Meeting - 6:30PM, Avondale Administration Building
Sign Up for Bond Planning Committee

Repeats From Previous Newsletters Repeats From Previous Newsletters

School Bond Funding School Bond Funding

How are bond funds received and spent?

Below is a timeline showing how school districts receive bond funds, and the process for allocating those funds.


**Note: Each year, Avondale undergoes a full annual audit of bond funds, revenues, and expenditures to ensure funds are being appropriately allocated.

open_in_new zoom_out_map

Avondale Bond Phases & Projects Avondale Bond Phases & Projects

When will projects begin?

Below is a timeline illustrating the various projects that will be completed throughout all phases of the bond.


**Note: This is a general overview. Project specifics and timelines are subject to change and will be determined with the assistance of planning committees.

open_in_new zoom_out_map

Next Scheduled Bond Update

The Avondale community can expect the next quarterly bond update in June of 2025. For more information, visit www.avondaleschools.org/bond.

Avondale School District
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter