SHANNON ES - MPR Project
June 2025

Project Updates - June 2025
Construction Activity
- Interior Construction: preparing for ceramic tile in the restrooms, finishing wall finish in preparation of interior paint, installing ductwork in the dining area
- Exterior Construction: installing sheet metal at parapets and completing the roofing and windows
- Site Work: installing the grease interceptor, stormwater system and canopy piers
Project Overview
Project Scope: The primary purpose of this project is to build a new multi-purpose room with a dining area, stage, food services kitchen, server, and support spaces. This project is an investment in our community through the use of taxpayer bond dollars.
Anticipated Completion: Fall/Winter 2025
After the completion of the new building, the existing portable cafeteria will be removed. The project will include roll-up doors to support connection to the exterior, landscaping around the building, and infrastructure for a new garden.
Anticipated Completion: Fall/Winter 2025
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Sign up here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net