September 22, 2025 Bond Update
Work Begins on the New Maintenance & Transportation ππͺπ§°
Bid Package 2A - Site Work & Prep
Exciting progress is underway as we move forward with the design of a new Transportation and Maintenance Building, which is set to begin construction this fall! Located just west of the current high school, this much-needed facility will replace outdated and undersized buildings that no longer meet modern safety standards.
Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker and shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.
This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.
Tree Removal/Replacement & Disc Golf Course
The disc golf course on the west side of the high school was recently removed to prepare for construction of the new transportation and maintenance facility, slated to begin this winter. About nine baskets and a number of trees had to be taken out, a step the district did not take lightly. We recognize how meaningful this wooded space and recreational area have been for students and neighbors, and we share the disappointment that comes with altering a natural setting. Our team is working carefully to limit environmental impact and is committed to thoughtful tree replacement as part of the project. We are also exploring possibilities for relocating the disc golf courseβpotentially off campusβso the community can continue to enjoy the game in a new setting.
Bid Opening for New Maintenance & Transportation Facilityππ§
On Friday, September 19, bids were opened on the construction of the new Maintenance & Transportation Facility. Stay tuned for more information coming soon!
Mattawan Schools Celebrates Phase One of Stadium Project with Ribbon Cutting
Mattawan Schools Celebrates Phase One of Stadium Project with Ribbon Cutting
Mattawan Consolidated Schools hosted a special ribbon cutting on Friday, September 5, 2025, to mark the completion of Phase One of the Mattawan Stadium project. The ceremony took place at 6:45 p.m., just moments before the 7:00 p.m. kickoff of the seasonβs first home football game.
Held at 56720 Murray Street in Mattawan, the celebration highlighted the stadiumβs new turf field and all-weather trackβkey upgrades designed to enhance athletic programs and community events for years to come. Student representatives joined district leaders, members of the Board of Education, and Superintendent R. Fleenor at midfield to officially cut the ribbon, symbolizing the start of an exciting new era for Wildcat athletics.
βWhen we step back and look at the whole picture, itβs clear: your investment is ushering our district boldly into the future,β said Superintendent Fleenor during the ceremony. βYou have given our children and grandchildren the tools to dream bigger, reach higher, and carry forward a legacy of excellence that will last for generations."
ON-GOING PROJECTS π
BID PACKAGE 1A - STADIUM WORK
Week 27
Week 27 marks a major milestone for BP1A, with the turf installation now fully complete. Additional line markings for soccer have been added to ensure clear field layout and flexibility for multi-sport use. The team also addressed some minor malfunctions with a few of the digital boards on the new scoreboard, troubleshooting issues that surfaced during recent events. Work on the track surface continues to progress steadily and remains on schedule for completion toward the end of October. Overall, the project is moving forward as planned and nearing its final phases.
π¨Take Note!π¨
Stadium Work, Phase 2 Summer 2026
It is important to note that the stadium will be renovated in multiple phases. Phase two, scheduled to begin in the Summer of 2026 and will include renovations to the current press box and the addition of a new sound system, as well as the completion of the home bleacher facing (top portion).
Stadium Work, Phase 3
Phase three will include the construction of a new entryway and concession on the south end of the current stadium, as well as cosmetic improvements to the current entryway on the North side of the stadium.
BP1A Contingency Update
BID PACKAGE 1C
BALL FIELDS GET SOME TLC βΎπ₯
Bid Package 1C is moving forward with Phase One of the softball and baseball field renovations. Construction is underway, bringing key upgrades to the infields, warning tracks, and outfield fences, along with the installation of new windscreens to enhance player safety and field appearance. Looking ahead, Phase Two is planned to explore additional improvements, including potential upgrades to the dugouts and press boxes, ensuring the facilities continue to meet the needs of athletes and fans alike.
Bid Package 1B - Traffic Flow Relief on the Way! ππ¦πΈ
Campus Traffic Flow Design is COMPLETEβ
Considerable planning has been accomplished in the redesign of the traffic flow in and around the middle and high school buildings. Based on observation and feedback, we feel we have the best plan possible to address safety and flow concerns. A few notables:
- Fully separate buses from carpool and staff traffic at both the middle and high schools
- Reconfigure the carpool traffic routes at both the middle and high schools
- Add needed parking in front of middle and high schools
- Add a through drive east to west for bus traffic to move within our district
- Open Holler Lane to all traffic coming in or out of the campus allowing for efficient flow
Above: concept design of bus loading lanes on the south side of the middle and high schools.
Below: concept design of parking and carpool lanes on the north side of middle and high schools.
Below: traffic flow patterns
Campus Wayfinding, Finds a Way ππππ
Extensive planning is underway to develop the most thorough and clear direction while navigating the campus.
UPCOMING IMPORTANT DATES
ARCHIVED INFORMATION
Construction Bid Packages Explained
Construction Bid Packages Explained
The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.
2024
Summer 2024
β Owner Direct β Replace Existing Soccer Lights
β Owner Direct β Technology Infrastructure (Switches, Wireless, HS Fiber Upgrades)
Fall 2024
β Owner Direct β Student Device Replacement Phase 1
Winter 2025
Owner Direct β Student Device Replacement Phase 2
2025
March β August 2025
Bid Package 1A β Football Stadium: Inner Scope
Summer 2025
Bid Package 1C β Baseball & Softball Field Improvements
β Bid Package 1D β HS Replace Fire Alarm System
β Bid Package 1E β HS Carpet Replacement
Fall 2025
Bid Package 1F β HS Gymnasium Cooling
Owner Direct β Auditorium (Band Shell, Pit Section, Lighting, Stage Floor, A/V, Curtain)
Nov 2025 β Oct 2026
Bid Package 2 β Transportation & Maintenance Facility
2026
March β September 2026
Bid Package 1B β Campus Traffic Flow
Sept 2026 β March 2028
Bid Package 4 β Field House
Bid Package 4 β Natatorium
Owner Direct β Replace CR Furniture: Summer 2026
2027
Summer 2027
Bid Package 3 β MS Upgrade Domestic Water Heaters
Bid Package 3 β MS Replace Fire Alarm System
Bid Package 3 β MS Replace Building Temperature Controls
Bid Package 3 β MS Replace Chiller & Associated Pumps
Bid Package 3 β MS Replace Boiler & Associated Pumps
Bid Package 3 β MS Add 3rd Boiler for Redundancy
Bid Package 3 β MS Classroom Wing Security Doors
Bid Package 6 β Upgrade Domestic Water Heaters
Bid Package 6 β Upgrade ECEC Gym AHUs to Include Cooling
March β August 2027
Bid Package 4 β Tennis Court Facility
June 2026 β August 2027 (overlapping start)
Bid Package 3 β MS Cafeteria Renovation
Sept 2027 β March 2028
Bid Package 6 β HS Weight Room Addition
2028
March β August 2028
Bid Package 6 β HS Locker Room Renovation
June 2026 β August 2028 (overlapping start)
Bid Package 3 β MS Front Office Expansion
Summer 2028
Bid Package 1B β Stadium Press Box Upgrades
Bid Package 5 β MS Replace Interior Lighting to LED
Bid Package 5 β MS Replace Ceiling Tiles (with Lighting Replacement)
Bid Package 5 β MS Replace Corridor Lockers
Bid Package 5 β MS Renovate Science Labs (8th & 7th Grade)
Bid Package 5 β MS Renovate Toilet Rooms
Bid Package 6 β HS Auditorium Exterior Upgrades
Bid Package 6 β HS Exterior Masonry Upgrades (@Entry Canopies)
Bid Package 6 β HS Replace Interior Lighting to LED
Bid Package 6 β HS Renovate Toilet Rooms
Bid Package 6 β HS Renovate Science Labs
Bid Package 6 β HS Replace Building Temperature Controls
Bid Package 7 β Practice Fields
Bid Package 7 β Baseball & Softball Upgrades
March β August 2028
Bid Package 4 β Multipurpose/Soccer Competition Field
2028 (No Month Specified)
Owner Direct β Bus Prop 2
TBD
Owner Direct β Replace Security Cameras
Owner Direct β Technology District Wide: Classroom Upgrades
Owner Direct β Technology District Wide: Large Spaces (Gymnasium A/V)
Bid Package 7 β Football Stadium: Outer Scope / Entry
Bold Designs for New Maintenance and Transportation Complex COMPLETE!β
Exciting progress is underway as we move forward with the design of a new Transportation and Maintenance Building, which is set to begin construction this fall! Located just west of the current high school, this much-needed facility will replace outdated and undersized buildings that no longer meet modern safety standards.
Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker and shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.
This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.
Our Plan. Our Students. Our Future.
Our focus revolves around five key objectives for the bond:
- Preserve existing assets
- Prioritize safety and security
- Provide future-focused academic and extracurricular experiences for our students
- Enhance infrastructure
- Demonstrate fiscal responsibility
Safety & Security:
- Addressing traffic congestion, lack of parking spaces, and separation of traffic and busing through enhancements
- Replacement of outdated, unreliable security equipment at each building
Transportation:
- Continued replacement of an aging bus fleet
Academic Learning Spaces + Experience:
- Replacement of original, aged classroom equipment and furniture at middle and high schools
- Updates to original, outdated science areas at middle and high schools (excluding the newly renovated portions) to ensure students have state of the art experiences.
Fine Arts:
- Upgrades to lighting and media equipment at the high school auditorium
Infrastructure:
- Replacement of original, outdated lockers, bathrooms, various ceilings, and lighting at middle and high schools
- Renovations to high school weight room including expansion to address overcrowding and scheduling issues for student-athletes and physical education courses
- Upgrade of aged building controls at middle and high schools (water, fire, HVAC, etc.) to provide the most efficient and safe environmental controls
- Addition of cooling to main gymnasiums at the high school
Student Athletic Experience:
- Renovation of aged high school locker rooms
- Renovation of the high school stadium, including artificial turf, new entryways, expanded concessions
- New high school track - the current track is backwards and nearly unusable in the current condition
- Upgrades to baseball and softball fields
- Construction of a new multi-use turf field (soccer, lacrosse, football)
- Maintenance of existing practice fields; addition of a new outdoor practice space
Other Construction:
- Addressing overcrowding in the current Middle School cafeteria
- Replacement of aged, quickly deteriorating tennis courts
- Replacement of aged transportation building and maintenance building
- Construction of a fieldhouse facility for indoor practice teams/band to address lack of 12-month practice space; available for community use
- Construction of a student/community pool