Stege Rebuild Project
August 2026

August 2026 - Project Updates
Upcoming Community Meeting
Please join us our next community update! The meeting is on August 25th from 6:30pm to 7:30pm at Booker T. Anderson Community Center.
Activities This Month
- Worked with regulatory agencies to secure approvals for upcoming project activities.
- DSA and Health Department approved Phase 2 documents.
- Resume removal of fuel tanks and associated materials.
- Start cut and fill grading operations.
- Perform major site grading and earthwork activities in preparation for the next phase of construction.
- Stabilize building pad areas in preparation for future construction activities.
Activities Next Month
- Stabilize site soils with lime treatment in preparation for future construction activities.
- Bid and finalize the contract for Phase 2 construction
- Start utilities in the public right-a-way
Announcement: Upcoming Lime Treatment
Lime treatment activities are scheduled to start on August 21st at the Stege Site. Lime treatment is a standard soil stabilization process used to prepare the ground for construction. All work will be completed by trained professionals following strict safety and environmental standards. Our construction management team will continuously monitor all activities.
Project Summary
The Stege campus rebuild will replace existing buildings with a new site layout. Students are temporarily located at DeJean Middle School.
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net