BOND UPDATE

November 2, 2026

BOND UPDATE November 2, 2026
BOND UPDATENovember 2, 2026

OCCUPANCY SCHEDULED FOR JANUARY 2027! 🀩 OCCUPANCY SCHEDULED FOR JANUARY 2027! 🀩

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

πŸ—οΈ Finishing Touches! 🚧

Construction continues to progress at the new Transportation and Maintenance Facility, with several important milestones reached this past week. Above-ceiling inspections have been approved, casework has been installed, and work continues on hard-lid ceilings. Exterior signage is now in place, along with the electrical inverter and fire alarm panel. Additional progress includes piping installation in the fluids room and the beginning of concrete floor sealing. Looking ahead, crews will continue mechanical, electrical, plumbing, and fire protection finishing work, complete additional ceiling work, install surface-mounted fixtures, and prepare the next section of concrete for sealing. We are excited to see the facility taking shape as work continues toward completion!


πŸ’™ A special thank you to our Mattawan community for your continued support! Your investment in our schools is helping us build modern, efficient facilities that will serve our students, staff, and community for years to come! 😍


πŸŽ‰We plan on finishing BP2 on time and on budget. Current balance contingency dollars will come back to the district to be reinvested in the bond elsewhere!

User uploaded image
zoom_out_map

Kitchen/Breakroom

User uploaded image
zoom_out_map

Mailboxes

User uploaded image
zoom_out_map

Fueling Station

User uploaded image
zoom_out_map Show in original size

BP 3 - MIDDLE SCHOOL OFFICE UNDERWAY BP 3 - MIDDLE SCHOOL OFFICE UNDERWAY

User uploaded image
zoom_out_map Show in original size

Footing Work Starts Next Week!πŸ‘£πŸΎπŸ‘

Update

Construction continues to move forward on the Middle School renovation and addition project. Recent progress includes forming and pouring concrete piers, footing extensions, and foundation walls, along with masonry work on the foundation. Looking ahead, crews will begin backfilling around the foundation walls and installing underground plumbing. These foundational steps represent important progress as the project continues to take shape!


Main Office Relocation and Redesign

The new main office layout strengthens security, improves daily workflow, and better serves students and families. The redesign includes:

  • More efficient staff workflow through a centralized, connected layout.

  • Integration of β€œThe Den” and student resource areas directly within the office suite for easier access and support.

  • Improved health room design to provide enhanced privacy, accessibility, and student care.

  • Consolidation of essential servicesβ€”placing all administrative and student support functions in one area rather than two.

User uploaded image
zoom_out_map Show in original size

BP3 MIDDLE SCHOOL CAFETERIA STARTS JUNE 2027 BP3 MIDDLE SCHOOL CAFETERIA STARTS JUNE 2027

User uploaded image
zoom_out_map Show in original size

Construction will run during the 27-28 School Year

Cafeteria Improvements Include:

The updated cafeteria design focuses on improving student experience, operational efficiency, and community use. Key benefits include:

  • Expanded seating capacity for approximately 400 students, allowing for more flexible scheduling and improved comfort.

  • Dedicated serving and preparation spaces, improving meal service flow and overall functionality.

  • Centralized location adjacent to the main office to enhance safety and supervision during the school day.

  • Proximity to the front of the building, providing convenient access for after-hours and community events.

  • Dedicated receiving area to streamline deliveries for operations and food service, reducing congestion and improving building safety.


Construction on the cafeteria is expected to begin in June 2027, with completion currently projected for March 2028. During this time, the existing cafeteria and kitchen will be unavailable as crews work to transform these spaces.



We are working closely with our construction partners, Veridus Advisors, AVB, and TowerPinkster, along with our middle school administration, food-service team, and building staff to develop a plan that allows construction and school operations to take place simultaneously,



Middle School families will receive a detailed communication on this in December, 2026.

User uploaded image
zoom_out_map Show in original size

BP 4 - 12 NEW TENNIS COURTS 🎾πŸ₯‡ BP 4 - 12 NEW TENNIS COURTS 🎾πŸ₯‡

Construction continues to progress steadily on the new tennis courts and surrounding site improvements. Recent work includes preparing the gravel base for the new parking lot, continuing storm sewer installation, installing catch basins, and beginning the installation of fence posts around the tennis courts. Crews have also completed forming the remaining courts in preparation for concrete pouring. Looking ahead, work will focus on continued grading of the new parking lot, pouring the concrete slabs for the final tennis courts, and advancing storm sewer and fencing installation. We are excited to see this project continue to take shape as we move closer to providing our students and community with these outstanding new facilities!


The courts are scheduled to open in July 2027.

User uploaded image
zoom_out_map Show in original size

BP 4 - AQUATIC CENTER & FIELD HOUSE BP 4 - AQUATIC CENTER & FIELD HOUSE

Construction is set to begin as early as June 2027!

Below are renderings based on current designs. This project is scheduled to be bid out in February, with demolition in May of 2027 and center construction tentatively scheduled to begin in June of 2027.


General Amenities:

  • 8 lanes
  • Diving Well
  • Seating for 350
  • Concessions (serves main stadium as well)
  • Fieldhouse
  • 2-lane track
  • 60-yard turf field


Please note: details may still change in some of the designs.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

NEW BAND SHELL!🎢🎢 NEW BAND SHELL!🎢🎢

User uploaded image
zoom_out_map Show in original size

PROJECTS ON DECK βœ… PROJECTS ON DECK βœ…

Middle School Old Labs, Toilet Rooms, Misc.

BP 5 - We are in schematic design for science labs, toilet rooms, and miscellaneous work at the middle school. Tentative schedules show bidding will go out in the Fall of 2027, with completion in the fall of 2028.

High School Weight Room, Locker Rooms, Toilet Rooms, & Old Labs

BP 6 - We are in schematic design for science labs, toilet rooms, and miscellaneous work at the middle school. Tentative schedules show bidding will go out in the Fall of 2027, with completion in the Fall of 2028.

User uploaded image
zoom_out_map Show in original size
Bond 2024 Website
General Bond 2024 Information
Mattawan Consolidated School
R. Fleenor is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter