Cameron ES Critical Needs Project
June 2023

Project Updates
Construction Completed Last Month
- Installation of ductwork, casework, and new accessible sinks are in progress
- Concrete was poured for the accessible walkway next to the drop-off zone
- Installation of drywall in the adjusted toilet and storage rooms
Upcoming Activities
- Patching and painting of the ceilings where ductwork was attached
- Install equipment enclosure CMU walls
- New asphalt at the drop-off area
- Begin site work associated with the new PG&E service
Project Overview
- Project Scope: Improvements to site HVAC Systems, Electrical Infrastructure, and Accessibility including path of travel improvements and parking lot updates.
-
Architect: PBK Architects
Anticipated Completion: Winter 2023