Lake ES -School Replacement Project

April 2024

Lake ES -School Replacement Project April 2024
Lake ES -SchoolReplacement ProjectApril 2024

Project Updates - April 2024 Project Updates - April 2024

Construction Activity Construction Activity

zoom_out_map

Building A - Office and Library

Ongoing work in Progress:

  • Interior door hardware
  • Wood Ceiling in the main office
  • Finishing touches on casework
  • Installing rubber base
  • Installing operable partition in the Library and Community Room
zoom_out_map

Building B and C - Classroom Buildings

Ongoing work in Progress:

  • Interior doors and hardware
  • Finishing touches on casework
  • Installing rubber base
  • Installing operable partitions in the Classrooms and Project Room
  • Installing acoustical paneling
zoom_out_map

Site Work

  • Installing concrete sidewalks around the front entryway
  • Ongoing installation of perimeter fencing
  • Pave the emergency access road and student drop-off

Project Overview Project Overview

  • Project Scope: The primary purpose of this project is to replace the school campus. Campus will be occupied during the duration of this project. The project will have two main construction phases. The first phase will include new buildings and site work on the East half of the campus and the second phase will include new buildings and remaining site work on the West half of the campus. Project design started in August 2021 and the first phase of construction is scheduled to start in Summer 2022. Construction for Phase 1 is scheduled through Summer of 2023 and Phase 2 is scheduled through Fall 2025. This project is an investment in our community through the use of taxpayer bond dollars.
  • Architect: Quattrocchi Kwok Architects - QKA
  • Anticipated Completion: Fall 2025
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
zoom_out_map

Flex Area

Wood ceiling and clerestory window

zoom_out_map
zoom_out_map

Flex Area

Study nooks
Lake Construction Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter