Bricks and Mortar: 03/18/2026
BRICKS AND MORTAR
Bricks and Mortar Update: Board of Education Regular Meeting, March 16, 2026
A meeting summary for Weston residents prepared by the Board of Education Communications Committee.
Background
The Weston Board of Education (BOE) is holding special monthly meetings from December 2025 until June 2026 to plan how to update Weston Public Schools’ (District) campus.
School construction and design experts joined the March 16, 2026 meeting to answer questions that BOE members had raised in previous meetings.
The BOE will be holding a public comment for the campus revitalization on March 23, 2026 at 7:00 pm in the Weston Middle School Library.
To learn more, you can watch the meeting here.
What We Learned at the Meeting
Reduced Estimated Probable Cost
SLAM Collaborative (SLAM), an architecture firm that specializes in school construction and design, reduced their estimated opinion of probable cost from their prior estimate.
- Renovate as New
- Total project cost: $121.7 – $127.9 million
- Estimated cost to Weston after state reimbursement: $101.3 – $106.5 million
- Build a New School
- Total project cost: $121.3 – $127.6 million
- Estimated cost to Weston after state reimbursement: $109.7 – $115.4 million
Additional Notes
- The cost per square foot aligns with similar middle school construction projects.
- The resulting building will be energy efficient and comply with all current codes.
- The amount that the State will reimburse the Town for the project is an estimate. The actual amount will depend on several factors.
Alternative Grade Configurations
- Adding 5th Grade to the Middle School
- SLAM provided this information in response to BOE member inquiry about whether including 5th grade in the middle school would increase reimbursement from the State.
- About 142 fifth-grade students would be added, for a total of about 696 students.
- The school would need an extra 12,000–15,000 square feet of space.
- Estimated total additional project cost: $12 – $15 million
- Estimated additional cost to Weston after state reimbursement: $9 – $12 million
- This will increase the state reimbursement rate for the entire project, which increases the amount of money the State will reimburse the Town.
- Can WIS be renovated to house grades PK-4?
- This option is not recommended for further consideration because it would require adding more classrooms, which would reduce outdoor play spaces and parking. In addition, wetlands on the property limit where the building and parking could be expanded.
Grants
There is a grant available to support energy-efficient buildings. However, the grant is awarded after the project is complete, and based on proof of the building’s energy efficiency. Additional grants might be available.
Timelines
Colliers, the District’s representative that helps with the state grant process, compared different timelines for seeking project funding approval, including how each option would affect planning, public support, and costs. They mentioned that a November 2026 Town referendum and a June 2027 State grant application submission would give the BOE more time to prepare while still keeping the full project schedule on track.
What’s Next?
BOE members will continue discussing the information that was shared during this meeting, including preferences for timelines, and start formulating a recommendation so they can vote on how to move forward at the March 30, 2026 meeting.
Where We’ve Been So Far
Education Specifications
In May 2024, the BOE developed and approved Educational Specifications (Ed Specs), which is a written plan for what the renovated or new middle school should include.
State Reimbursement Process
At the December 1, 2025 special meeting, SLAM and other professionals explained how the state grant process works in order to receive state reimbursement for school construction.
Town and District Capital Improvements
First Selectwoman Samantha Nestor joined the January 7, 2026 special meeting to share information about the Town’s capital projects, and the District administration presented its 10-year capital improvement plan for other campus needs in addition to the middle school.
Grade Configurations
At the January 7, 2026 special meeting, BOE members asked the District administration to consider the educational impact of various grade configurations housed within a school. District administration presented a comparative analysis of grade configuration models at the February 2, 2026 general meeting.
SLAM Phase II Investigation
At the February 23, 2026 meeting, members of architecture firm SLAM presented their Phase II investigation of the middle school.
Renovate as New vs Build New Middle School
At the March 2, 2026 meeting, BOE members agreed that based on the estimates provided in SLAM’s Phase II investigation, building a new middle school is preferable to renovating the existing middle school. They agreed that more work is needed to try and reduce the estimated probable cost to Weston.
Previous Bricks and Mortar Summaries
Read the summary of the December 1, 2025 and January 7, 2026 meetings.
Read the summary of the February 23, 2026 meeting.
Read the summary of the March 2, 2026 meeting.
All Campus Revitalization Information Gathered to Date
Visit the Campus Revitalization section of the District website to see all prior studies, meetings, presentations, and newsletters.
The BOE Communications Committee will continue to issue summaries of the special meetings on this topic. We welcome you to provide feedback and share your thoughts at a public comment on March 23, 2026 at 7:00 pm at the Middle School Library. You can find the link to watch via live stream in the District Calendar at www.westonps.org.