Time to Bloom Update 9/14/25

A monthly update on the RTMSD K-1 Early Learning Center

Time to Bloom Update 9/14/25 A monthly update on the RTMSD K-1 Early Learning Center
Time to BloomUpdate 9/14/25A monthly update on the RTMSD K-1 Early LearningCenter

Board of School Directors Work Session Presentation - Land Development Board of School Directors Work Session Presentation - Land Development

RTMSD Superintendent Joseph Meloche and the team from ICS/Schrader Group provided updates about the progress since June 2025 on the district's K-1 Early Learning Center. A recording of the full presentation is available on our YouTube channel. The slide show presentation is available on the RTMSD website.

The Land Development portion of the update included:

  1. An overview of the site, including bus drop-off, car drop-off, visitor parking and staff parking
  2. Refined schematic drawings of the building's interiors and exteriors
  3. An explanation of the Land Development Process, which includes a rigorous process of approvals from Middletown Township, Delaware County, DEP and PennDot. The Land Development Process must be completed prior to obtaining a building permit
  4. Milestones in the Land Development Process:
  • Traffic Scoping Document submitted and comments received
  • Presented Sketch Plan to Township on 9/3/25
  • Traffic Study anticipated in October/November 2025
  • Submission of Preliminary Land Development Drawings anticipated in October/November 2025
  • Meeting with Township Planning Commission in November/December 2025 for Preliminary Land Development
  • Submission of NPDES application in January/February 2026

Proposed Timeline Proposed Timeline

Proposed Project Milestones 2025-2028

The following are the proposed start and finish dates related to the project:

March 2025-June 2025: Schematic Design

June 2025-October 2025: Design Development, with Approval of Act 34 Resolution in November 2025 and Act 34 Hearing in January 2026

November 2025-May 2026: Construction Documents

June 2025-August 2026: Bidding, with Board Approval of Bids in August 2026

September 2026-August 2028: Construction

August 2028: Move-in

Budget Update Budget Update

Athletics Fields Project Added to Project Costs

The costs of the Athletics Fields improvements of the Penncrest multi-sport synthetic turf complex (Baseball, Softball, Soccer) and parking expansion have been added to the budget for the K-1 Center. Associated costs have updated the total budget from $84,000,000 to $91,480,000. Details on budget items may be found on the slide show presentation and on the video of the presentation at Work Session Meeting.

TIME TO BLOOM WEB PAGE
Learn more! Our Time to Bloom web page offers more information about the K-1 Early Learning Center project and a portal for submitting your questions and input.