October 16 , 2025

Bond Update

October 16 , 2025 Bond Update
October 16 , 2025Bond Update

Board Meeting Update October 13, 2025 Board Meeting Update October 13, 2025

User uploaded image
zoom_out_map

The Board of Education took action on the following bond items at its October 13 meeting:


Bid Pack 2 Guaranteed Maximum Price (GMP) Amendment Maintenance & Transportation Building – Concrete & Sitework Only

The District completed the competitive bid process for all necessary work needed to complete the Maintenance & Transportation Building (Bid Pack 2). [Tree clearing & the Pre-engineered Metal Building was done prior] AVB conducted post bid interviews with lowest responsible bidders but are only recommending to award contracts for concrete & sitework at this time. There is other review that needs to occur in the other areas of the project before awarding those sub-contractor contracts. The GMP amount of this contract amendment for concrete & sitework is $1,647,134. This amount does not include construction owner contingencies, required payment & performance bonds and the construction manager fees since those will be included in the final amendment with the remaining contracts.


BP2 Maintenance & Transportation Bldg.- Parking Lot Lighting Resolution

Parking lot lighting for the Maintenance & Transportation Building are part of Bid Pack 2 however the District is recommending purchasing the lighting materials through Musco, separately from the rest of the project. The cost of the parking lot lighting is $86,010 for materials only. Installation will be part of the Bid Pack 2 GMP presented by AVB in November. This purchase is being made through cooperative purchasing with Sourcewell, which satisfies the competitive bid process in the State of Michigan.


School Loan Revolving Fund - Borrowing for November 2025 Debt Retirement Payments Resolution

It is necessary for the district to borrow funds to meet the debt retirement payments on its outstanding bonds due November 1, 2025. For these payments the district must borrow an amount not more than $1,082,419.


Bond Sale Resolution

The Board approved issuing $1,000,000 of Proposal 2 – 2024 Bonds in September 2025 so the district can start paying for expenses associated with Proposal 2 projects. The sale of the bonds occurred 10/9/2025 with JPMorgan Chase being awarded the purchase of the $1,000,000 bond issuance with a 10-year term and an interest rate of 3.62%. There were three (3) proposals in total to choose from. The remainder of the approved Proposal 2 bonds will likely be issued late fall 2026.


The board of education received a monthly update regarding the school construction bond.


Click on the link below for the full report.


High Level Highlights:

BP 1A – Stadium / Track / Field Work

  • Scope: New track surface & field events, new turf, stormwater, fencing, sidewalks.

  • Budget: $6.67M (GMP $5.79M, with $510k total contingency).

  • Schedule: Substantial completion and ribbon cutting by Sept 5, 2025.

  • Phase 2: Pressbox, new PA system, home bleacher risers (completion Aug 2026).

  • Recent change orders:

    • Play-clock controls ($4,883)

    • Flagpole prep ($1,550)

    • Storm drain conflicts ($27,537, in process)

  • Remaining contingency: $94,422.

BP 1C – Baseball/Softball Fields

  • Scope: Fencing, irrigation, grading.

  • Budget: $750K.

  • Completion: October 2025.

BP 2 – Maintenance & Transportation Facility

  • Scope: New maintenance/transportation building.

  • Budget:

    • $1.44M approved (PEMB & tree clearing).

    • $1.65M current request (concrete & sitework).

    • Final GMP approval slated for November 2025.

  • Completion: November 2026.

BP 1B – Campus Traffic Flow / HS Gym Cooling / Stadium Press Box

  • Timeline: Currently in Design Development phase.

  • Construction: Spring–Fall 2026.

BP 3 – Middle School Renovation

  • Scope: Cafeteria expansion, front office addition, fire alarm, HVAC, chillers, boilers.

  • Timeline: Construction Summer 2026–Fall 2027.

BP 4 – Natatorium, Field House, Tennis & Multipurpose Fields

  • Timeline: Construction Fall 2026–Spring 2028.

MS/HS Furniture Replacement

  • Kickoff & design: October–November 2025.

  • Purchase order due: January 2026.

  • Installation: June–July 2026.

  • Final walkthrough: August 2026.

Future Projects (Conceptual Stage)

High School:

  • Weight room & locker room remodel

  • Science labs, classrooms, auditorium exterior, restrooms

  • Mechanical upgrades

Middle School:

  • Lockers, ceiling tiles, science labs, restrooms

Technology:

  • Classroom projectors and audio systems

pdf
insert_drive_file
Mattawan BOE Presentation- October 2025
Download
3.4 MB

ON-GOING PROJECTS 📆 ON-GOING PROJECTS 📆

BID PACKAGE 2A - MAINTENANCE & TRANSPORTATION BID PACKAGE 2A - MAINTENANCE & TRANSPORTATION

User uploaded image
zoom_out_map Show in original size

Bid Package 2A - Site Work & Prep

✅ Site clearing is complete.


✅ On Oct. 13, the Board of Education approved additional site and concrete work—construction work, including site grading, will begin this week or next.


✅ The Design Team is reviewing the full bid scope of this project and will bring remaining items, including a Guaranteed Maximum Price (GMP), to the November board meeting.


Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker-and-shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.


This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.


Tree Removal/Replacement & Disc Golf Course

The disc golf course on the west side of the high school was recently removed to prepare for construction of the new transportation and maintenance facility, slated to begin this winter. Approximately nine baskets and several trees were removed, a step the district did not take lightly. We recognize how meaningful this wooded space and recreational area have been for students and neighbors, and we share the disappointment that comes with altering a natural setting. Our team is working carefully to limit environmental impact and is committed to thoughtful tree replacement as part of the project. We are also exploring possibilities for relocating the disc golf course—potentially off campus—so the community can continue to enjoy the game in a new setting.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

BID PACKAGE 1A - STADIUM WORK BID PACKAGE 1A - STADIUM WORK

This week brought the striping of the new track, the last major item in Phase 1 of the Stadium renovation!

User uploaded image
zoom_out_map Show in original size

🚨Take Note!🚨 🚨Take Note!🚨

User uploaded image
zoom_out_map

Stadium Work, Phase 2 Summer 2026

It is important to note that the stadium will be renovated in multiple phases. Phase two, scheduled to begin in the Summer of 2026 and will include renovations to the current press box and the addition of a new sound system, as well as the completion of the home bleacher facing (top portion).

Stadium Work, Phase 3

Phase three will include the construction of a new entryway and concession on the south end of the current stadium, as well as cosmetic improvements to the current entryway on the North side of the stadium.

BP1A Contingency Update BP1A Contingency Update

User uploaded image
zoom_out_map Show in original size

BID PACKAGE 1C BID PACKAGE 1C

Ball Field Snipit
User uploaded image
zoom_out_map

BALL FIELDS GET SOME TLC ⚾🥎

Bid Package 1C is moving forward with Phase One of the softball and baseball field renovations. Construction is underway, bringing key upgrades to the infields, warning tracks, and outfield fences, while new windscreens enhance player safety and field appearance.


✅ Irrigation is installed at the baseball field.


✅ Irrigation installation for the softball field is scheduled for this week.


✅ Fencing is being installed this week.


Looking ahead, Phase Two will include planning for additional improvements, such as upgrades to the dugouts and press boxes, ensuring the fields continue to meet the needs of athletes and fans alike.

User uploaded image
zoom_out_map Show in original size

BID PACKAGE 1B - Traffic Flow Relief on the Way! 🚌🚦🚸 BID PACKAGE 1B - Traffic Flow Relief on the Way! 🚌🚦🚸

User uploaded image
zoom_out_map Show in original size

Campus Traffic Flow Design is COMPLETE✅

Considerable planning has been accomplished in the redesign of the traffic flow in and around the middle and high school buildings. Based on observation and feedback, we feel we have the best plan possible to address safety and flow concerns. A few notables:


  • Fully separate buses from carpool and staff traffic at both the middle and high schools
  • Reconfigure the carpool traffic routes at both the middle and high schools
  • Add needed parking in front of middle and high schools
  • Add a through drive east to west for bus traffic to move within our district
  • Open Holler Lane to all traffic coming in or out of the campus allowing for efficient flow


Above: concept design of bus loading lanes on the south side of the middle and high schools.

Below: concept design of parking and carpool lanes on the north side of middle and high schools.

User uploaded image
zoom_out_map Show in original size

Below: traffic flow patterns

User uploaded image
zoom_out_map Show in original size

UPCOMING IMPORTANT DATES UPCOMING IMPORTANT DATES

User uploaded image
zoom_out_map Show in original size

ARCHIVED INFORMATION ARCHIVED INFORMATION

Construction Bid Packages Explained Construction Bid Packages Explained

User uploaded image
zoom_out_map

Construction Bid Packages Explained

The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.


2024

  • Summer 2024

    • ✅Owner Direct – Replace Existing Soccer Lights

    • ✅Owner Direct – Technology Infrastructure (Switches, Wireless, HS Fiber Upgrades)

  • Fall 2024

    • ✅Owner Direct – Student Device Replacement Phase 1


Winter 2025

  • Owner Direct – Student Device Replacement Phase 2


2025

  • March – August 2025

    • ALMOST COMPLETE - Bid Package 1A – Football Stadium: Inner Scope

  • Summer 2025

    • UNDERWAY - Bid Package 1C – Baseball & Softball Field Improvements

    • ✅Bid Package 1D – HS Replace Fire Alarm System

    • ✅Bid Package 1E – HS Carpet Replacement

  • Fall 2025

    • DESIGN PHASE - Bid Package 1F – HS Gymnasium Cooling

    • ✅Owner Direct – Auditorium (Band Shell, Pit Section, Lighting, Stage Floor, A/V, Curtain)

  • Nov 2025 – Oct 2026

    • SET TO BEGIN SOON - Bid Package 2 – Transportation & Maintenance Facility


2026

  • March – September 2026

    • DESIGN PHASE - Bid Package 1B – Campus Traffic Flow

  • Sept 2026 – March 2028

    • DESIGN PHASE - Bid Package 4 – Field House

    • DESIGN PHASE - Bid Package 4 – Natatorium

  • Owner Direct – Replace CR Furniture: Summer 2026


2027

  • Summer 2027

    • Bid Package 3 – MS Upgrade Domestic Water Heaters

    • Bid Package 3 – MS Replace Fire Alarm System

    • Bid Package 3 – MS Replace Building Temperature Controls

    • Bid Package 3 – MS Replace Chiller & Associated Pumps

    • Bid Package 3 – MS Replace Boiler & Associated Pumps

    • Bid Package 3 – MS Add 3rd Boiler for Redundancy

    • Bid Package 3 – MS Classroom Wing Security Doors

    • Bid Package 6 – Upgrade Domestic Water Heaters

    • Bid Package 6 – Upgrade ECEC Gym AHUs to Include Cooling

  • March – August 2027

    • Bid Package 4 – Tennis Court Facility

  • June 2026 – August 2027 (overlapping start)

    • DESIGN PHASE - Bid Package 3 – MS Cafeteria Renovation

  • Sept 2027 – March 2028

    • Bid Package 6 – HS Weight Room Addition


2028

  • March – August 2028

    • Bid Package 6 – HS Locker Room Renovation

  • June 2026 – August 2028 (overlapping start)

    • DESIGN PHASE - Bid Package 3 – MS Front Office Expansion

  • Summer 2028

    • Bid Package 1B – Stadium Press Box Upgrades

    • Bid Package 5 – MS Replace Interior Lighting to LED

    • Bid Package 5 – MS Replace Ceiling Tiles (with Lighting Replacement)

    • Bid Package 5 – MS Replace Corridor Lockers

    • Bid Package 5 – MS Renovate Science Labs (8th & 7th Grade)

    • Bid Package 5 – MS Renovate Toilet Rooms

    • Bid Package 6 – HS Auditorium Exterior Upgrades

    • Bid Package 6 – HS Exterior Masonry Upgrades (@Entry Canopies)

    • Bid Package 6 – HS Replace Interior Lighting to LED

    • Bid Package 6 – HS Renovate Toilet Rooms

    • Bid Package 6 – HS Renovate Science Labs

    • Bid Package 6 – HS Replace Building Temperature Controls

    • Bid Package 7 – Practice Fields

    • Bid Package 7 – Baseball & Softball Upgrades

  • March – August 2028

    • Bid Package 4 – Multipurpose/Soccer Competition Field

  • 2028 (No Month Specified)

    • Owner Direct – Bus Prop 2


TBD

  • Owner Direct – Replace Security Cameras

  • Owner Direct – Technology District Wide: Classroom Upgrades

  • Owner Direct – Technology District Wide: Large Spaces (Gymnasium A/V)

  • Bid Package 7 – Football Stadium: Outer Scope / Entry

Our Plan. Our Students. Our Future. Our Plan. Our Students. Our Future.

User uploaded image
zoom_out_map

Our focus revolves around five key objectives for the bond:


  1. Preserve existing assets
  2. Prioritize safety and security
  3. Provide future-focused academic and extracurricular experiences for our students
  4. Enhance infrastructure
  5. Demonstrate fiscal responsibility


Safety & Security:

  • Addressing traffic congestion, lack of parking spaces, and separation of traffic and busing through enhancements
  • Replacement of outdated, unreliable security equipment at each building

Transportation:

  • Continued replacement of an aging bus fleet

Academic Learning Spaces + Experience:

  • Replacement of original, aged classroom equipment and furniture at middle and high schools
  • Updates to original, outdated science areas at middle and high schools (excluding the newly renovated portions) to ensure students have state of the art experiences.

Fine Arts:

  • Upgrades to lighting and media equipment at the high school auditorium

Infrastructure:

  • Replacement of original, outdated lockers, bathrooms, various ceilings, and lighting at middle and high schools
  • Renovations to high school weight room including expansion to address overcrowding and scheduling issues for student-athletes and physical education courses
  • Upgrade of aged building controls at middle and high schools (water, fire, HVAC, etc.) to provide the most efficient and safe environmental controls
  • Addition of cooling to main gymnasiums at the high school

Student Athletic Experience:

  • Renovation of aged high school locker rooms
  • Renovation of the high school stadium, including artificial turf, new entryways, expanded concessions
  • New high school track - the current track is backwards and nearly unusable in the current condition
  • Upgrades to baseball and softball fields
  • Construction of a new multi-use turf field (soccer, lacrosse, football)
  • Maintenance of existing practice fields; addition of a new outdoor practice space

Other Construction:

  • Addressing overcrowding in the current Middle School cafeteria
  • Replacement of aged, quickly deteriorating tennis courts
  • Replacement of aged transportation building and maintenance building
  • Construction of a fieldhouse facility for indoor practice teams/band to address lack of 12-month practice space; available for community use
  • Construction of a student/community pool
User uploaded image
zoom_out_map Show in original size

Additional Information at your Fingertips Additional Information at your Fingertips

User uploaded image
zoom_out_map

Supporting Docments

Click on the buttons below to review salient information

Bond 2024 Website
General Bond 2024 Information
User uploaded image
zoom_out_map

Construction

User uploaded image
zoom_out_map

Architect

User uploaded image
zoom_out_map

Owner's Representative

Mattawan Consolidated School
R. Fleenor is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter