Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE

Renaissance @ Rand Renaissance @ Rand

Project Status: February 6, 2026

Project Completion: 73% complete

Current Status: Boiler #1 is complete; Boiler #2 is nearing completion,

Upcoming Milestones: Boiler feed unit is to be installed. Final electrical will be scheduled after Boiler #2 is plumbed in

Contract to Date: $3,785,100.00 This is for all boiler replacements
Paid to Date: $2,898,075.00

User uploaded image
zoom_out_map Show in original size

George Inness George Inness

Project Status: February 6, 2026

Project Completion: 75% complete

Current Status: Boilers #1 and #2 are installed, pending rear exhaust dampers and wiring

Upcoming Milestones: Boiler feed unit installation to be completed

User uploaded image
zoom_out_map Show in original size

Bradford Elementary Bradford Elementary

Project Status: February 6, 2026

Project Completion: 74% complete

Current Status: Boiler #1 is complete; Boiler #2 is next on the list for completion

Upcoming Milestones: Rear exhaust dampers final installation and wiring to be completed. Boiler feed unit install to be completed. Final electrical will be scheduled after Boiler #2 is fully plumbed in.

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Watchung Elementary Watchung Elementary

Project Status: February 6, 2026

Project Completion: 75% complete

Current Status: Boilers #1 and #2 are complete except for insulation

Upcoming Milestones: Rear exhaust damper final installation and wiring to be completed. Final electrical is completed for programming and 2nd boiler Start up

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Edgemont Elementary Edgemont Elementary

Project Status: February 6, 2026

Project Completion: 74% complete

Current Status: Boiler 1 is complete, Boiler #2 is nearing completion

Upcoming Milestones: Rear exhaust damper final installation and wiring, the Boiler feed unit is in place and needs to be piped in

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Northeast Elementary Northeast Elementary

Project Status: February 6, 2026

Project Completion: 72% complete

Current Status: Boiler 1 is complete; Boiler #2 is nearing completion

Upcoming Milestones: Rear exhaust damper final installation and wiring still open, the Boiler feed unit is to be installed

User uploaded image
zoom_out_map Show in original size

Newsletters Updates

November of 2022, in a historic show of unity, more than 80% of town voters backed the $188 million Bond Referendum to repair and modernize Montclair Public Schools' long-neglected buildings and decaying infrastructure (11 schools and the administration building constructed more than 99 years ago on average).

launch montclair.k12.nj.us
User uploaded image
zoom_out_map Show in original size
Conor O'Brien- Principal
Legacy Construction Management
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter