Montclair Public Schools
September 16, 2024
Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE
Renaissance @ Rand
Project Status: February 6, 2026
Project Completion: 73% complete
Current Status: Boiler #1 is complete; Boiler #2 is nearing completion,
Upcoming Milestones: Boiler feed unit is to be installed. Final electrical will be scheduled after Boiler #2 is plumbed in
Contract to Date: $3,785,100.00 This is for all boiler replacements
Paid to Date: $2,898,075.00
George Inness
Project Status: February 6, 2026
Project Completion: 75% complete
Current Status: Boilers #1 and #2 are installed, pending rear exhaust dampers and wiring
Upcoming Milestones: Boiler feed unit installation to be completed
Bradford Elementary
Project Status: February 6, 2026
Project Completion: 74% complete
Current Status: Boiler #1 is complete; Boiler #2 is next on the list for completion
Upcoming Milestones: Rear exhaust dampers final installation and wiring to be completed. Boiler feed unit install to be completed. Final electrical will be scheduled after Boiler #2 is fully plumbed in.
Watchung Elementary
Project Status: February 6, 2026
Project Completion: 75% complete
Current Status: Boilers #1 and #2 are complete except for insulation
Upcoming Milestones: Rear exhaust damper final installation and wiring to be completed. Final electrical is completed for programming and 2nd boiler Start up
Edgemont Elementary
Project Status: February 6, 2026
Project Completion: 74% complete
Current Status: Boiler 1 is complete, Boiler #2 is nearing completion
Upcoming Milestones: Rear exhaust damper final installation and wiring, the Boiler feed unit is in place and needs to be piped in
Northeast Elementary
Project Status: February 6, 2026
Project Completion: 72% complete
Current Status: Boiler 1 is complete; Boiler #2 is nearing completion
Upcoming Milestones: Rear exhaust damper final installation and wiring still open, the Boiler feed unit is to be installed