BOND UPDATE

October 13, 2026

BOND UPDATE October 13, 2026
BOND UPDATEOctober 13, 2026

OCCUPANCY SCHEDULED FOR JANUARY, 2027! 🀩 OCCUPANCY SCHEDULED FOR JANUARY, 2027! 🀩

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

πŸ—οΈ Transportation & Maintenance Facility Completion Close! 🚧

Exciting progress continues on Mattawan's new Transportation & Maintenance Facility! Recent work includes asphalt paving, installation of ceiling grids and lighting, continued ductwork and insulation, parking lot striping, and painting of the steel in the service bays.


πŸ”¨ Looking ahead, crews will continue interior finishing, electrical and mechanical work, and begin installing fluid piping in the service areas.


πŸ’™ A special thank you to our Mattawan community for your continued support! Your investment in our schools is helping us build modern, efficient facilities that will serve our students, staff, and community for years to come! 😍


πŸŽ‰We plan on finishing BP2 on time and on budget. Current balance contingency dollars will come back to the district to be reinvested in the bond elsewhere!

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map Show in original size

DEMO OF MAINTENANCE TO BEGIN IN MAY! 🚧 DEMO OF MAINTENANCE TO BEGIN IN MAY! 🚧

Existing Maintenance and Parts of Transportation Demoed to Make Way for Aquatic Center and Field House

Demolition will begin in May of the current maintenance facility. The areas impacted are noted in red below.

User uploaded image
zoom_out_map Show in original size

Portions of the current transportation facility will also be demolished. Please note these in blue below. The yellow portion will be retained for campus storage.


NOTE: This demolition will make way for the new Aquatic Center, Field House, and additional parking.

User uploaded image
zoom_out_map Show in original size

BP 3 - MIDDLE SCHOOL OFFICE/CAFETERIA πŸ˜€πŸ”† BP 3 - MIDDLE SCHOOL OFFICE/CAFETERIA πŸ˜€πŸ”†

User uploaded image
zoom_out_map Show in original size

Footing Work Starts Next Week!πŸ‘£πŸΎπŸ‘

Cafeteria Improvements

The updated cafeteria design focuses on improving student experience, operational efficiency, and community use. Key benefits include:

  • Expanded seating capacity for approximately 400 students, allowing for more flexible scheduling and improved comfort.

  • Dedicated serving and preparation spaces, improving meal service flow and overall functionality.

  • Centralized location adjacent to the main office to enhance safety and supervision during the school day.

  • Proximity to the front of the building, providing convenient access for after-hours and community events.


Main Office Relocation and Redesign

The new main office layout strengthens security, improves daily workflow, and better serves students and families. The redesign includes:

  • More efficient staff workflow through a centralized, connected layout.

  • Integration of β€œThe Den” and student resource areas directly within the office suite for easier access and support.

  • Improved health room design to provide enhanced privacy, accessibility, and student care.

  • Consolidation of essential servicesβ€”placing all administrative and student support functions in one area rather than two.

  • Dedicated receiving area to streamline deliveries for operations and food service, reducing congestion and improving building safety.

Summary

This design revision supports the district’s goals of maximizing existing resources, enhancing safety and efficiency, and improving both student and community experiences. By renovating and expanding the current spaces, the district achieves a more functional, secure, and cost-effective solution that supports long-term operational excellence.



Note below: green shading is the proposed new cafeteria footprint; blue is the new main office construction; purple is the current student services office. The stand-alone area is 'The Den.'

User uploaded image
zoom_out_map Show in original size

BP 4 - 12 NEW TENNIS COURTS 🎾πŸ₯‡ BP 4 - 12 NEW TENNIS COURTS 🎾πŸ₯‡

User uploaded image
zoom_out_map Show in original size

Work continues to move forward on the BP4 East project! Crews are currently building up the site pad, continuing excavation at the retention pond, and removing and salvaging existing fencing. 🚜 The progress photos show significant earthwork taking shape across the future tennis court area and surrounding site. The courts are scheduled to open in July 2027.


🎾 Coming up next: crews are expected to build an access road for upcoming concrete work and begin staking the tennis courts.


AS A REMINDER, part of the bond campaign is to be intentional about tree replacement. It will not necessarily be a one-to-one program, but the team is committed to replanting as wide a variety of trees as possible. For example, in the middle school project alone (new offices and parking out front), we are tentatively scheduled to plant over 100 trees throughout the north side of campus.


Pictured below: tennis court prep.

User uploaded image
zoom_out_map Show in original size

BP 4 - AQUATIC CENTER & FIELD HOUSE BP 4 - AQUATIC CENTER & FIELD HOUSE

Construction is set to begin as early as June, 2027!

Below are renderings based on current designs. This project is scheduled to be bid out in February, with demolition in May of 2027 and center construction tentatively scheduled to begin in June of 2027.


General Amenities:

  • 8 lanes
  • Diving Well
  • Seating for 350
  • Concessions (serves main stadium as well)
  • Fieldhouse
  • 2-lane track
  • 60-yard turf field


Please note: details may still change in some of the designs.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

UPDATE - NEW RAILINGS INSTALLED at STADIUM! UPDATE - NEW RAILINGS INSTALLED at STADIUM!

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

BP 1B UPDATE - CAMPUS TRAFFIC FLOW PHASE 1 BP 1B UPDATE - CAMPUS TRAFFIC FLOW PHASE 1

User uploaded image
zoom_out_map Show in original size

Phase 1 is complete. Current Balance Contingencies will roll over into Phase 2, occurring in the summer of 27.

πŸŽ‰We finished Phase 1 on time and on budget.


Phase 2 is outlined in purple below.

User uploaded image
zoom_out_map Show in original size

PROJECTS ON DECK βœ… PROJECTS ON DECK βœ…

Middle School Old Labs, Toilet Rooms, Misc.

BP 5 - We are in schematic design for science labs, toilet rooms, and miscellaneous work at the middle school. Tentative schedules shows bidding will go out in the Fall of 2027 with completion in the Fall 0of 2028.

High School Weight Room, Locker Rooms, Toilet Rooms, & Old Labs

BP 6 - We are in schematic design for science labs, toilet rooms, and miscellaneous work at the middle school. Tentative schedules shows bidding will go out in the Fall of 2027 with completion in the Fall 0of 2028.

OVERALL BOND BY BID, BUDGET & COMPLETION OVERALL BOND BY BID, BUDGET & COMPLETION

Summary of major projects by bid package, budget, and substantial completion.

User uploaded image
zoom_out_map Show in original size

Summary of major projects completed to date!

User uploaded image
zoom_out_map Show in original size
Bond 2024 Website
General Bond 2024 Information
Mattawan Consolidated School
R. Fleenor is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter