Construction Corner
May 2025 - August 2026
Very long video, but has ALL the information and breakdown of the project! Grab some πΏ and enjoy!
ππππ¦Ίπ§ It's About Time!!! ππππ¦Ίπ§
McCullough has a long and storied history. We opened in 1976 as a High School, had stints of housing Freshman and Sophomores as the Woodlands High School McCullough Campus, and now 7th and 8th graders as McCullough Junior High. There have been additions and updates to the campus throughout the years like the addition of the Bock auditorium in 2001, the additions of some classrooms in some parts of the building, and a few modernizations. But as a whole, the campus looks very much the same as it did in the late 70's!
Well, McCullough Junior High is getting the updates it deserves! I am so excited to share the construction plans that are a part of CISD's 2023 bond allocated for classroom additions and improvements for our campus! Before getting into the details, here are some highlights:
- Adding general classrooms
- Adding a 3rd gym
- Creating dispersed and centralized admin pods that meet current standards (2 existing admin areas displaced by building additions)
- Re-building art rooms to meet current standards (in form of an addition)
- Renovating existing art rooms to become a choir hall that meets current standards and a second theater classroom with proximity to the auditorium
- Renovating life skills classrooms
- Creating dedicated SPED resource rooms
- Converting both floors of existing library to classrooms
- Displacing library to a new, centralized location on the 2nd floor
- Creating student collaboration spaces
- Creating dedicated instructional intervention rooms
- Re-piping the entire AC system
- Re-roofing the entire campus
- Replacing all lighting and ceiling grids
- Remodel of front reception and waiting area
McCullough will shine brighter than ever, continuing to be a symbol of pride for former McCullough High School graduates, current and future McCullough Junior High students, and the entire Woodlands community. β€οΈπβ€οΈπ
π§π¨ 04/09/2026 UPDATE!π¨π§
Updated drone shots! Project is still on target to be completed by August.π
- Once exterior portions of the new additions are complete, things will really start moving along!
- In the drone shots, you can really start to see the 3rd gym, lobby, and 3 new art rooms taking shape.
- You can also see the new classroom and science lab additions on the East end of the building taking shape.
- In the coming weeks, you will start to see the new library coming to life over the car port/U-drive up front!
π§π¨ 03/04/2026 UPDATE!π¨π§
I received some updated drone shots of the project and wanted to share them! The project is moving along and is still scheduled to be completed in August of this year (2026). In the images you can see:
- Addition of the 3rd gym and 3 new art classrooms on the West (Car Rider) side.
- Addition of classrooms, computer labs, and science labs on the West side (Bus Ramp Side).
- Continued renovation of the U-Drive and new library on the South side of the building.
As a bonus.... check out that car rider line all nice and neat and ready to pick up kiddos!!π₯³π
I will try to find a time where I can get some updated interior renovation shots of these spaces as well.
Enjoy!
π§π¨ 01/08/2026 UPDATE!π¨π§
- Interior renovations (Admin Pods, New Classrooms, Collaboration Spaces) are done!
- New floors, ceiling grid, ceiling tile, and walls completed in some areas
- Front horseshoe, Upstairs A Hall, and office area under construction now for new library and front reception area
- East addition coming together. Structure is up and they are preparing to pour concrete floors for second floor)
- West addition (Gym, Art Classrooms, Lobby) is in progress. Walls are up and they are starting to assemble the interior structure
- New flooring in Band Hall, Orchestra Hall, and Choir Room
- New LED lighting in cafeteria, renovated classrooms, and renovated hallways. Rest of building will be completed throughout the project
- Bock Auditorium renovations finishing up
- Updating of lighting continues around the campus and in classrooms
- HVAC continues to be updated and piping replaced
π§π¨ 11/10/2025 UPDATE!π¨π§
- Progress is moving along! The project is still on schedule at this time!
- East slab poured
- West slab poured
- 3rd Gym taking shape
- Interior renovations continue
- Tile beginning to be placed in main corridors along walls
- Interior classroom additions where old library was located are starting to come together
- Admin pods are beginning to take shape
- Updating of lighting continues around the campus and in classrooms
- HVAC continues to be updated and piping replaced
π§π¨ 09/10/2025 UPDATE!π¨π§
- Interior renovations continue on schedule, while the exterior additions are slightly behind due to the rain in recent weeks.
- Below you will see photos of the in-filling of the former stairwell connecting the old upstairs and downstairs library! Concrete will go in this week.
- They have begun framing the classrooms and office spaces in the interior renovations. These will become our two other "Admin" pods as well as classrooms both downstairs and upstairs.
- A/C ductwork and piping renovations continue throughout the building
- Also included are some areal shots to show the current state of the exterior additions! You can start to see the shape of the additional areas on the East and West sides of the building!
π§π¨ 07/16/2025 UPDATE!π¨π§
- Interior work zones starting to come together! Temp walls are up and painted.
- Starting the interior of one of the new admin "pods". This will house our counselors for the Fall semester until their permanent offices are complete and ready in the Spring.
- First set of cleaning crews arrive on Monday (7/21). They, along with our CISD custodial cleaning crew will begin a deep clean to prepare for the school year. We will be ready for visitors at orientations!
π§π¨ 07/01/2025 UPDATE!π¨π§
- Most (If not all) interior demo is complete for the current phase!
- Temporary walls are starting to go up separating the construction areas from the rest of the building and hallways.
- Our to porte-cocheres have officially been sealed off.
- West side (Car-Rider) has been officially sealed off as well.
- Next up: Cleaning! Cleaning crews will start arriving in the coming weeks to clean the mess inside the building to get it ready for teachers and staff to return.
- New bus ramp still needs to be poured.
- Exterior renovations and building additions will continue as scheduled.
π§π¨ 06/23/2025 UPDATE!π¨π§
- Demo on the interior of the building has been moving right along. They are hoping to be done with this phase of the project's interior demo this week.
- Both upstairs and downstairs demo mostly complete.
- Classrooms that are being renovated or enlarged demo has mostly been complete.
- They have started demo on the "Fan" rooms on the East side of the building, and those should be coming down soon in preparation of the East side addition.
- Demo has begun on the exterior of the building on both the West and East sides of the building!
- Both porte-cochère's on each side are starting to come down.
- They should start prepping the area for the new bus ramp soon.
- Portables are starting to arrive. It will be a bit before they are set up, though.
- HVAC piping is starting to be replaced in areas of the building. AC has been going out periodically which has NOT been fun. π
- It has been fun watching the process, but loud and dusty. They will come and clean the interior of the building before staff returns at the end of Summer, once interior demo is complete.
Here are some pictures of the progress!
π§π¨ 06/05/2025 UPDATE!π¨π§
Project is under way!
Off to the races! Construction crews have started several parts of the project. Here are the current updates:
- On the East side of the building, crews have begun tearing up the old bus ramp. The current ramp loops through the area the new building addition will be located. They will re-design and re-pour the new bus ramp in the coming weeks.
- The center of the building renovations have begun. Crews are starting the demo of our old upstairs and downstairs library. This area will eventually be renovated to additional classrooms, admin pods, and collaboration spaces! So cool!!
- The have started the temporary walkway covering around the Bock auditorium. This will provide cover during foul weather to students walking to our new car-rider doors during construction.
The End Game. What it will all look like!
Here are some renderings on what different areas of the building will look like at the completion of the project! Please keep in mind that some of the "details" like interior and exterior graphics, paint, furniture, etc. are just there for the renderings. Details like those will be finalized as the project moves along and gets closer to completion. But at least you can get an idea!
Front Port-O-Cochere and Library
Library Interior
West Side of Building (Car Rider)
Car Rider Entrance and Third Gym
Car Rider Entrance and Third Gym
Entrance Lobby (Car Rider)
Entrance Lobby (Car Rider) Looking at Third Gym/Athletic Lobby
Athletic Lobby (By Third Gym) Looking Back at Entrance Lobby
East Side of Building (Bus Ramp)
East Side of Building (Bus Ramp)
First Floor Collaboration Space
Second Floor Collaboration Space
Logistics Changes During Construction
So.....Now that I have buttered you up with all the cool stuff, let's talk about how getting all that cool stuff created is going to modify things for next school year!π¬π€£
Car Rider
Due to construction, materials, and fencing, our car rider procedures and layout will be different for the duration of the 2025 - 2026 school year. We have made every effort to work with construction and planning to minimize the impact on our car rider line and staging process. Here are the details:
Here is the new "Car Rider" path and procedures for this year. There are several BIG changes as compared to years past, so please read through this information carefully!
- WE ARE REVERSING THE FLOW THIS YEAR! π¬
- After the BTS Bash run-through, we realize that efficiency and flow will be the name of the game this year.
- The old path was designed to stage and get as many vehicles off S. Panther Creek as possible. Without parking this year for parent staging, traffic is going to be rough regardless of how many we can get off the street and into the parking lot.
- Essentially, we are choosing flow-rate over capacity.
New Route
- This year, you must enter car-rider line from the right lane of the West-bound side of S. Panther Creek.
- The left lane will be for through-traffic only.
- All center "Crossover" sections will be blocked with cones.
- Essentially, you turn right into the car rider line, continue through the path, pick up your kiddo, and continue to the exit where you will turn right back onto S. Panther Creek.
- There will be "Loading Zones" along the path where students and parents can text each other to let them know where they are in the loading area.
- We are basically re-routing the right lane of S. Panther Creek through our parking lot for car rider.
- While still slow, this should significantly increase flow-rate and efficiency with not having to temporarily block traffic, etc.
The Benefits
- No more having to block through-traffic to let people out.
- No more having to block parents from entering or exiting to allow through-traffic or busses to pass.
- Kids are loading on the passenger side of the vehicle now, and not having to go around vehicles to enter, significantly increasing safety.
- Allows a path for teachers or athletic busses to enter or exit the parking lot during car-rider traffic.
- Prevent S. Panther Creek West of the school coming East from becoming blocked in the single-lane section due to traffic.
- Greatly simplifies the entire process since entry and exit points don't cross-over each other, Right turn in, right turn out, done.
- Limits the number of staff needed to direct and stop traffic, increasing the number of staff that can be utilized to organize and monitor students in the car-rider line waiting.
Potential Detriments
- Since there is only one way in, traffic WILL be backed-up in the right lane of S. Panther Creek, and will almost certainly wrap down Woodlands Parkway right lane.
- I would rather have that, where there are still plenty of lanes on Woodlands Pkwy for through traffic, versus blocking the single lane of S. Panther Creek that is West of the campus.
Very Important Notes
- It is VERY IMPORTANT this year that you pull ALL the way up in line when available. Basically right to where the construction trailer is.
- There will NOT be any "staging" areas in the parking lot this year for parents to drop off kids in the morning, or arrive early for afternoon dismissal. Due to limited parking availability for the staff this year due to construction, staff will have to park in the West parking lot.
- There will be a "passing lane" available in the car line to go around other vehicles that are loading/unloading. Please be VERY CAREFUL if passing a loading or unloading vehicle.
- You will enter from S. Panther Creek and follow the path laid out by the red arrows on the map.
- Please only pick up or allow your student out of the car once you have safely stopped next to the safety barriers on the drivers side of the vehicle. These provide a safe place for students to walk as they make their way to the building.
- Please do everything in your (and your kiddos π¬) power to exit the vehicle as quickly as possible so we can keep the line moving!
- A small, collapsible umbrella may be a good addition to you students daily items for when it is raining during arrival/dismissal.
- Safety will be our top priority as always. This is new for us, as well as y'all as parents. Please, please, please keep your head on a swivel as you make your way through the car rider line.
- Once you exit the parking lot, you will be forced to turn right on S. Panther Creek, and will not be allowed to cross and turn left.
- I made a video (linked below) that gives you a visual and walks you through the entire new process. Please be sure to watch it so you have an idea of what everything will look like day 1.
- Please pack your patience. Due to the nature of our circumstances, car-rider will simply not be as quick and efficient as it was last year. We all will have to make "Lemonade out of Lemons" this year as we navigate all these changes together!
- The front horseshoe opens after 8:45 am for late student drop off, and is CLOSED for student pick ups at dismissal.
Building Entrances
Car Rider
Our current West entrance that we use for Car Riders will not be accessible all year due to the new building addition.
- For the entire school year, our new Car Rider entrance will be the double doors on the South side of the building between the Bock auditorium and the main building. Please see pictures below for reference.
- There will be a temporary covering installed over the sidewalk that is wrapping around the Bock and into those doors. This will provide coverage for students entering the building if it is raining.
- Students will exit out of these same doors in the afternoon and head to the Car Rider line.
- As we finalize arrival and dismissal procedures and plan this summer, we will communicate more details and logistics involving Car Rider line procedures!
Main Front Entrance
Ok, so this one will be different depending on the semester..... Here is the breakdown:
- Fall Semester
- Front horseshoe drive and front office will operate as normal. No changes expected!
- Spring Semester
- The front horseshoe and whole front of the building will be blocked and inaccessible due to the library construction.
- The front entrance to the building will become the SAME entrance as Car Riders, which are the double doors pictured above.
- There will be a portable placed adjacent to the Bock auditorium for the entire year. During the Spring semester ONLY, this portable will house our amazing front receptionists, and will be our "Front Office" for the Spring semester.
- Parents who need to check-in or check-out a kiddo, drop something off, attend a meeting, or basically anything else you would normally come to the front office to check-in for, you will now be doing it in the front portable.
- Parents will park in the West parking lot, walk around the Bock auditorium, and be buzzed into the secure gate that will be placed around the portable area. You would then enter the portable and speak with the receptionist.
- Again, this will be for the Spring semester only, and front office operations will be the same as they currently are in the Fall.
Modifications, Safety, and Logistics INSIDE the Building During the School Year
Construction in the Building π§π·
- Safety will be THE top priority (As always!)
- All construction areas will be walled off with no access for students or staff
- Construction workers who are working on the inside of the building will have ONE designated entrance to enter the building.
- Areas where construction workers are entering the building or walking to their workspace will be walled off as well.
- Basically the workers aren't going to see or interact with the students, and visa-versa.
- There could be residual impacts on construction in and around the building such as:
- Additional noise
- Temporary power flickering or potential power outages
- Areas of the building that we may have to temporarily change transitions of students due to work
- Potentially having to relocate classes to other areas due to unforeseen circumstances, etc.
- We will communicate with Planning and Construction to limit work or potential distractions on days like STAAR testing, important events on campus, etc.
- If there is any change to any of the plans, or something arises during the school year, I will communicate with you via this newsletter and my Hughes Huddle videos!
HVAC Replacement βπ₯Ά
- Our entire HVAC cooling system will be re-piped during the project (YAY!!!π)
- This will hopefully prevent leaks, and blowouts that we have had due to our "vintage" 70's and 80's piping.
- This process will involve miles of new piping to be installed throughout the building, old piping removed, and the system be recharged and tested.
- Because of the scope of this work, here are a few notes regarding the HVAC piping replacement:
- All main corridors and hallways WILL NOT have ceiling times in place for the entire 2025 - 2026 school year as they work on the HVAC piping.
- All restrooms, locker rooms and changing areas, and cafeteria area WILL have ceiling tiles in place, and any work in those areas will be limited to weekends, evenings, or Summer.
- Classrooms WILL have ceiling tiles in place during the school year. Construction will coordinate with me on the sections of classrooms that they plan to work on and when, and will complete the work in the evenings and weekends to limit or prevent any classroom disruption
- The AC charge, and change-over will take place in the Summer of 2026, so should have no effect on the AC during the school year.
- If there is any change to any of the plans, or something arises during the school year, I will communicate with you via this newsletter and my Hughes Huddle videos!
Before and After School Events Next Year π
- Although a "general and rough" estimate, main construction work and workers will be between 7(ish) am and 3(ish) pm daily. Obviously this is a guestimate, but should apply to the bulk of the main construction.
- We will still hold after school events from Fine Arts, Theater, Athletics, etc. This will be dependent on a few factors, however:
- The Bock Auditorium will be under renovation and unavailable in the Fall semester. This could limit activities and events, of cause them to be relocated to another location if a large event. We will obviously communicate that as events are scheduled and throughout the Summer and Fall.
- Space, and certain areas in the building, could be limited or off limits during construction for after school events.
- As of now, BOTH current gyms should not be affected by construction and available though out the year.
- Parking for events will be limited. The auxiliary West "gravel" parking lot will be fenced in and occupied during the day by construction crew parking. In the evening they will leave the gates open for us for additional parent parking if needed.
- If there is any change to any of the plans, or something arises during the school year, I will communicate with you via this newsletter and my Hughes Huddle videos!
So What's The Timeline On ALL This Stuff????
Best Laid Plans.......
In all these moving parts, production deadlines, material supplies, unforeseen circumstances, weather, any other potential road-block that could come up......We have to remember that plans are great and all, but they could change!
- The following is a TENTATIVE timeline on the project and what to expect as it moves along. NONE of this is set in stone, and there are so many variables in a construction project this size that there are certainly no guarantees!
- I will update this newsletter throughout the project if anything changes in the timeline!
May/Summer of 2025
- You will start to see construction fencing, equipment, and trailers showing up in and around the West side parking lot, specifically in the North parking lot on the West side of the building
- Note that our car rider line will remain the SAME for the duration of this school year (2024 - 2025)
- Construction on the East and West sides of the building as well as renovations in the interior of the building will begin sometime on or after June 2nd, 2025
- The building will be closed to outside activities or events for the Summer
Fall of 2025
- Construction continues on the East and West sides of the building as well as renovations inside the building
- New Car Rider path and entry into the building begins, and continues for duration of school year.
- Bock Auditorium closed for the Fall semester due to renovation.
- Front entrance to school still available, and front office remains operational as normal
Spring 2026
- Construction continues on the East and West sides of the building as well as renovations inside the building.
- Bock Auditorium scheduled to be back online.
- New Car Rider path and entry into the building continues as in the Fall.
- Front horseshoe driveway closed
- Current front office and port-o-cochere closed
- Front reception moved to portable located outside of Bock Auditorium
Summer 2026
- Construction on East and West side of building as well as interior renovations scheduled to finish
- HVAC piping replacement finishes up and AC system switched over to new piping/system.
- Building will be closed due to scheduled power and AC outages as construction finalizes
Fall 2026
- If ALL goes as planned, the stars and planets align, and luck holds out, the project should be completed and the IMPROVED McCullough Junior High is open for business!!
- Just in time for our 50th Birthday!π¬ππ
Town Hall Presentation
I will be offering a construction presentation town hall. I will essentially be presenting a slightly more detailed version of my Hughes Huddle construction video presentation that is linked at the top of this newsletter. I will also be able to answer any questions that you might have.
- Date: Monday, May 19th
- Time: 6:00 pm
- Place: Bock Auditorium at McCullough Junior High
Moving Forward.....
- I will provide updates to this construction newsletter throughout the project.
- Any new updates will be added at the top of the newsletter so they are easy to find and visible!
- I will advertise updates added to the construction newsletter in my Hughes Huddle videos or emails to families to make you aware to re-visit the newsletter.
- As next school year draws closer, be looking for some more detailed information about:
- Orientation and beginning of the year events/plans
- Logistics
- Arrival Procedures
- Dismissal Procedures
- Updates on events that my be affected by construction
- And basically other things that I am sure I am not thinking about right now.....π¬
Thank you for taking the time to read all the way to this point!! We are SO looking forward getting through this experience and seeing the AMAZING things that will come from it!!! We appreciate your support as always!!!!!β€πβ€π
McCullough JHS Contact Information
Main Office.....................................832.592.5100
24-hour Attendance Line...............832.592.5111
McCullough Fax.............................832.592.5116
Clinic...............................................832.592.5122
Clinic Fax........................................832.592.5127
Counselor's Office..........................832.592.5194
Registrar..........................................832.592.5114