Palmer Project Update April 2026
Actualización del Proyecto Palmer, abril de 2026
Palmer Staff, Students, and Families,
I want to take a moment to share a brief update on the Palmer High School project. I know many of you have been wondering where things stand following the City Council meeting on March 10, and I appreciate your patience as we have continued to move through this process.
Personal, alumnos y familias de Palmer,
Me gustaría dedicar un momento a compartir una breve actualización sobre el proyecto del instituto Palmer. Sé que muchos de ustedes se han estado preguntando cuál es la situación actual tras la reunión del Ayuntamiento del 10 de marzo, y les agradezco su paciencia mientras seguimos avanzando en este proceso.
Construction Progress
Construction continues to move forward on the new academic wing. As of this week, we are approximately 69% complete with structural panel installation, with 552 of just over 700 panels set.
We are also preparing for a major milestone: a topping out celebration on May 13, when the final panel will be set.
In the days leading up to that event, the final panel will be available for students, staff, and alumni to sign before it is lifted into place. Principal Burke will share additional details as they are finalized. Our goal is to align timing so that seniors are able to participate before their last day on campus.
In addition, the next phase of the project, renovation of the heart of the existing school, will begin this summer, starting with abatement work.
The new academic wing remains on track to open in February 2027.
Construction also reflects strong local partnership and long-term investment in the building. The structural panels being installed are manufactured locally by Stresscon and transported to campus, where they are lifted into place by crane. To date, 45 trade partners have been hired, 91% of which are local to El Paso County. Work is also well underway on the geothermal system that will support heating and cooling for the building, including completion of 150 wells and more than 30 miles of underground piping.
Avances en la construcción
Las obras de la nueva ala académica siguen avanzando. A fecha de esta semana, hemos completado aproximadamente el 69 % de la instalación de los paneles estructurales, con 552 paneles colocados de un total de algo más de 700.
También nos estamos preparando para un hito importante: la celebración de la colocación de la última viga el 13 de mayo, cuando se instalará el último panel.
En los días previos a ese evento, el último panel estará disponible para que los estudiantes, el personal y los antiguos alumnos lo firmen antes de que se coloque en su sitio. El director Burke compartirá más detalles a medida que se vayan concretando. Nuestro objetivo es coordinar los plazos para que los alumnos de último curso puedan participar antes de su último día en el campus.
Además, la siguiente fase del proyecto, la renovación del núcleo de la escuela actual, comenzará este verano, empezando por los trabajos de descontaminación.
La nueva ala académica sigue en camino de abrir sus puertas en febrero de 2027.
La construcción también refleja una sólida colaboración local y una inversión a largo plazo en el edificio. Los paneles estructurales que se están instalando son fabricados localmente por Stresscon y transportados al campus, donde se colocan en su sitio mediante grúa. Hasta la fecha, se ha contratado a 45 socios comerciales, el 91 % de los cuales son de la zona del condado de El Paso. También están muy avanzados los trabajos en el sistema geotérmico que se encargará de la calefacción y la refrigeración del edificio, incluida la finalización de 150 pozos y más de 30 millas de tuberías subterráneas.
Boulder Street Update
Following the March 10 City Council meeting, where the Boulder Street right-of-way vacation did not pass, Council later approved a motion to reconsider the item. A new hearing has been scheduled for May 26.
We are currently in that process. Over the past several weeks, we have been working closely with City staff and continuing conversations with City leadership to better understand the questions raised and to prepare additional information for the upcoming hearing. Because this is an active legislative process, we have been taking care to move thoughtfully and share information at appropriate points. The May 26 hearing will provide an opportunity to present a more complete picture and respond to the questions that were raised.
If the right-of-way vacation is ultimately approved, we will move forward accordingly. If it is not, we will return to the Steering Committee process to carefully evaluate next steps and ensure we are making the right decisions for the Palmer community.
Novedades sobre la calle Boulder
Tras la sesión del Consejo Municipal celebrada el 10 de marzo, en la que no se aprobó la renuncia al derecho de paso de la calle Boulder, el Consejo aprobó posteriormente una moción para volver a examinar el asunto. Se ha programado una nueva audiencia para el 26 de mayo.
Actualmente nos encontramos en ese proceso. Durante las últimas semanas, hemos estado trabajando en estrecha colaboración con el personal municipal y manteniendo conversaciones con los dirigentes de la ciudad para comprender mejor las cuestiones planteadas y preparar información adicional para la próxima audiencia. Dado que se trata de un proceso legislativo en curso, hemos actuado con cautela y hemos compartido la información en los momentos oportunos. La audiencia del 26 de mayo nos brindará la oportunidad de presentar un panorama más completo y responder a las preguntas que se han planteado.
Si finalmente se aprueba la renuncia al derecho de paso, seguiremos adelante en consecuencia. Si no es así, volveremos al proceso del Comité Directivo para evaluar cuidadosamente los próximos pasos y asegurarnos de que tomamos las decisiones correctas para la comunidad de Palmer.
Addressing Rumors
I also want to address a question that has come up directly. There are no plans to sell the Erps property for housing or any other purpose.
The master plan includes a full-sized baseball field, softball field, and tennis courts on that site. This plan was approved by the Board of Education, and it is our full intention to carry it forward.
As always, if you have questions or would like more information, please feel free to reach out to me directly at jessica.wise@d11.org.
Thank you for your continued engagement and support of Palmer High School. We will continue to provide updates as we move forward.
Sincerely,
Jessica Wise
Executive Director of Engagement
Colorado Springs School District 11
Aclaración de rumores
También quiero abordar una pregunta que se ha planteado directamente. No hay planes de vender el terreno de Erps para la construcción de viviendas ni para ningún otro fin.
El plan maestro incluye un campo de béisbol de tamaño reglamentario, un campo de sóftbol y pistas de tenis en ese emplazamiento. Este plan fue aprobado por la Junta de Educación, y tenemos la firme intención de llevarlo a cabo.
Como siempre, si tiene alguna pregunta o desea más información, no dude en ponerse en contacto conmigo directamente en jessica.wise@d11.org.
Gracias por su compromiso y apoyo continuos hacia Palmer High School. Seguiremos proporcionando información actualizada a medida que avancemos.
Atentamente,
Jessica Wise
Directora Ejecutiva de Participación
Distrito Escolar 11 de Colorado Springs