Lake ES -School Replacement Project
August 2023

Project Updates - March 2024
Construction Activity
Building A - Office and Library
Ongoing work in Progress:
- Final connections for fire alarm and data
- Installing wall covering in the library and main office
- Installing acoustic ceiling tile and wood plank ceiling
- Installing markerboards
- Hanging interior doors
- Commissioning the HVAC systems
Building B and C - Classroom Buildings
Ongoing work in Progress:
- Final connections for fire alarm and data
- Complete flooring
- Installing acoustic ceiling tile and wood plank ceiling
- Installing markerboards
- Hanging interior doors
- Start and Commission the HVAC systems
Site Work
- Installing concrete sidewalks and plazas between the buildings
- Beginning perimeter fencing
- Installing curb and gutter on the emergency access road and student drop-off
Project Overview
- Project Scope: The primary purpose of this project is to replace the school campus. Campus will be occupied during the duration of this project. The project will have two main construction phases. The first phase will include new buildings and site work on the East half of the campus and the second phase will include new buildings and remaining site work on the West half of the campus. Project design started in August 2021 and the first phase of construction is scheduled to start in Summer 2022. Construction for Phase 1 is scheduled through Summer of 2023 and Phase 2 is scheduled through Fall 2025. This project is an investment in our community through the use of taxpayer bond dollars.
- Architect: Quattrocchi Kwok Architects - QKA
- Anticipated Completion: Fall 2025
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Site Work
Forming the curb along the emergency access road
Main Street
Preparing for concrete between the Library and classroom buildings