KHS Modernization Project

October 2026

KHS Modernization Project October 2026
KHS ModernizationProjectOctober 2026

October 2026 - Project Updates October 2026 - Project Updates

User uploaded image
zoom_out_map

Activities This Month

Building A

  • Footing rebar and anchor bolts are complete
  • Continued slab-on-grade preparation including concrete form work
  • Installing under slab plumbing, and electrical conduit
  • Advanced elevator pit construction, including wall reinforcing, forming, waterproofing, and concrete placement
  • Continued coordination and design review activities associated with the Vaper Intrusion Mitigation System

Building B

  • Completed stage footing concrete placement
  • Footing rebar and anchor bolts are complete
  • Continued slab-on-grade preparation including concrete form work
  • Advanced elevator pit construction, including wall reinforcing, forming, waterproofing, and concrete placement
  • Completed canopy pier drilling, rebar installation, and concrete placement
User uploaded image
zoom_out_map

Activities Next Month

Building A

  • Complete stem wall concrete placement
  • Install under slab piping vents and rock base materials in the classroom area
  • Continue electrical conduit installation
  • Begin preparations for the slab including rebar reinforcing steel and vapor barrier
  • Complete elevator pit wall pours and form removal

Building B

  • Started structural steel erection!
  • Complete elevator pit wall pours and form removal
  • Continued coordination and design review activities associated with the Vaper Intrusion Mitigation System
User uploaded image
zoom_out_map Show in original size

Project Overview Project Overview

Phase 1 scope includes Building A - Office & Classrooms and Building B - Cafeteria and Performance Space
zoom_out_map Show in original size

Phase 1.3 Scope

This current phase of work includes two new buildings, the staff/visitors parking lot, and a remodel of the K Quad. Building A is a two-story classroom building along Cutting Blvd with the administrative, student services, and health center offices in the eastern wing. Building B is a combination performing arts and cafeteria supported by a full-cook kitchen, stage, and back of house areas.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.



Interested in serving? Apply here: bit.ly/CBOCWCCUSD23

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Anchor Bolts and Rebar

User uploaded image
zoom_out_map

Pier Drilling

Outdoor covered patio foundations for an outdoor dining area
KHS Modernization Project Newsletter
WCCUSD Facilities Planning & Construction