KHS Modernization Project
October 2026

October 2026 - Project Updates
Activities This Month
Building A
- Footing rebar and anchor bolts are complete
- Continued slab-on-grade preparation including concrete form work
- Installing under slab plumbing, and electrical conduit
- Advanced elevator pit construction, including wall reinforcing, forming, waterproofing, and concrete placement
- Continued coordination and design review activities associated with the Vaper Intrusion Mitigation System
Building B
- Completed stage footing concrete placement
- Footing rebar and anchor bolts are complete
- Continued slab-on-grade preparation including concrete form work
- Advanced elevator pit construction, including wall reinforcing, forming, waterproofing, and concrete placement
- Completed canopy pier drilling, rebar installation, and concrete placement
Activities Next Month
Building A
- Complete stem wall concrete placement
- Install under slab piping vents and rock base materials in the classroom area
- Continue electrical conduit installation
- Begin preparations for the slab including rebar reinforcing steel and vapor barrier
- Complete elevator pit wall pours and form removal
Building B
- Started structural steel erection!
- Complete elevator pit wall pours and form removal
- Continued coordination and design review activities associated with the Vaper Intrusion Mitigation System
Project Overview
Phase 1.3 Scope
This current phase of work includes two new buildings, the staff/visitors parking lot, and a remodel of the K Quad. Building A is a two-story classroom building along Cutting Blvd with the administrative, student services, and health center offices in the eastern wing. Building B is a combination performing arts and cafeteria supported by a full-cook kitchen, stage, and back of house areas.
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Anchor Bolts and Rebar
Pier Drilling
Outdoor covered patio foundations for an outdoor dining area