Lake ES -School Replacement Project
February 2026

Project Updates - February 2026
Construction Activity
Activities This Month
Complete irrigation and planting, fencing and gates, the turf playfield system, and punch list items.
Commission the mechanical, electrical and plumbing systems at the new cafeteria building.
Activities Next Month
- The project will be completed on-site by the beginning of March. The new turf area and garden will be open and ready for use by the end of February. Start the establishment and 90-day maintenance period for the hydroseeded planting areas.
The Completion of Lake Elementary School Campus
The Completion of lake Elementary School Campus
Thank you for following the project updates for Lake Elementary School up until the end, and congratulations to the Lake community for a beautiful new school that will house students for many years to come.
Project Overview
Project Scope: This project will replace the school campus, which will remain occupied throughout construction. It represents an investment in our community using taxpayer-funded bond dollars.
The project is divided into two main construction phases. Design began in August 2021.
- Phase 1 included new buildings and site work on the east half of the campus and was completed in Fall 2024.
- Phase 2 focused on new buildings and remaining site work on the west half of the campus, and is scheduled for completion in Winter 2025/26.
Anticipated Completion: Winter 2025/26
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net