Stege Rebuild Project
March 2026

March 2026 - Project Update
Activities This Month
- Continue underground main trunk lines for storm water, sewer water, domestic and fire water systems.
Activities Next Month
- Start mass grading and lime treat the site. Continue installation of underground stormwater systems
- COMMUNITY UPDATE MEETING in April. More information to come!
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Project Summary
The Stege campus rebuild, now in the design phase, will replace existing buildings with a new site layout. Students are temporarily located at DeJean Middle School.