Cameron ES Critical Needs Project
July 2023

Project Updates - July 2023
Construction Completed Last Month
- Patching and painting of the ceilings where ductwork was attached
- Construction of equipment enclosure
- New asphalt at the drop-off area
- Installation of new main entrance exterior doors
Upcoming Activities
- Painting of the ductwork
- Install equipment enclosure CMU walls
- New asphalt at the drop-off area
- Begin site work associated with the new PG&E service
Project Overview
- Project Scope: Improvements to site HVAC Systems, Electrical Infrastructure, and Accessibility including path of travel improvements and parking lot updates.
-
Architect: PBK Architects
Anticipated Completion: Winter 2023
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Accessible Restroom
Fixture installation in the revamped student restroom
Fan Coil Unit
Connecting ductwork to the new fan coil unit