KHS Modernization Project
September 2025

September 2025 - Phase 1 Demolition
Construction Activities
- Application of exterior water barriers, roof flashing and stucco finish is ongoing where the 100 and 200 building were adjacent to the 300 and 400 buildings
- New underground utilities to be installed this month
- Structural improvements to the 800 building
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
800 Building
New Parapet
400 Building
Water barrier and stucco