Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE

Renaissance @ Rand Renaissance @ Rand

Project Status: October 17, 2025

Project Completion: 48% complete

Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler

Upcoming Milestones:

Contract to Date: $3,785,100.00
Paid to Date: $845,451.88

User uploaded image
zoom_out_map Show in original size

George Inness George Inness

Project Status: October 17, 2025

Project Completion: 48% complete.

Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler .

Upcoming Milestones:

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Bradford Elementary Bradford Elementary

Project Status: October 17, 2025

Project Completion: 48% complete.

Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler

Upcoming Milestones:

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Watchung Elementary Watchung Elementary

Project Status: October 17, 2025

Project Completion: 48% complete.

Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler

Upcoming Milestones:

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Edgemont Elementary Edgemont Elementary

Project Status: October 17, 2025

Project Completion: 43% complete.

Current Status: Existing Boiler has been test fired and confirmed operational. Contractor to begin continue with piping and burner installation of new boiler.

Upcoming Milestones:

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
User uploaded image
zoom_out_map

Northeast Elementary Northeast Elementary

Project Status: October 17, 2025

Project Completion: 48% complete.

Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler

Upcoming Milestones:

Newsletters Updates

November of 2022, in a historic show of unity, more than 80% of town voters backed the $188 million Bond Referendum to repair and modernize Montclair Public Schools' long-neglected buildings and decaying infrastructure (11 schools and the administration building constructed more than 99 years ago on average).

launch montclair.k12.nj.us
User uploaded image
zoom_out_map Show in original size
Conor O'Brien- Principal
Legacy Construction Management
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter