Montclair Public Schools
September 16, 2024
Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE
Renaissance @ Rand
Project Status: October 17, 2025
Project Completion: 48% complete
Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler
Upcoming Milestones:
Contract to Date: $3,785,100.00
Paid to Date: $845,451.88
George Inness
Project Status: October 17, 2025
Project Completion: 48% complete.
Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler .
Upcoming Milestones:
Bradford Elementary
Project Status: October 17, 2025
Project Completion: 48% complete.
Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler
Upcoming Milestones:
Watchung Elementary
Project Status: October 17, 2025
Project Completion: 48% complete.
Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler
Upcoming Milestones:
Edgemont Elementary
Project Status: October 17, 2025
Project Completion: 43% complete.
Current Status: Existing Boiler has been test fired and confirmed operational. Contractor to begin continue with piping and burner installation of new boiler.
Upcoming Milestones:
Northeast Elementary
Project Status: October 17, 2025
Project Completion: 48% complete.
Current Status: New Boiler has been test fired and confirmed operational. Contractor to begin demolition and removal of 2nd boiler
Upcoming Milestones: