Lake ES -School Replacement Project

January 2025

Lake ES -School Replacement Project January 2025
Lake ES -SchoolReplacement ProjectJanuary 2025

Project Updates - January 2025 Project Updates - January 2025

zoom_out_map

Construction Activity

Building E and F (Kindergarten Wings)
  • Rough framing is mostly complete
  • Complete roof framing and begin the roof underlayment
  • Continue installing in wall and above ceiling piping, duct work, and conduit
zoom_out_map

Building D (Cafeteria)

  • The main floor slab has been poured
  • The stage slab is formed and will be completed this month
  • Framing will begin after the slab is completed
  • Continue to install pier footings for canopies

Project Overview Project Overview

  • Project Scope: The primary purpose of this project is to replace the school campus. Campus will be occupied during the duration of this project. The project has two main construction phases. The first phase included new buildings and site work on the East half of the campus and the second phase will include new buildings and remaining site work on the West half of the campus. Project design started in August 2021 and the first phase of construction is complete. Phase 2 is scheduled through Fall 2025. This project is an investment in our community through the use of taxpayer bond dollars.
  • Architect: Quattrocchi Kwok Architects - QKA
  • Anticipated Completion: Fall 2025
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.


Sign up here: bit.ly/CBOCWCCUSD23

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
zoom_out_map

Completed Roof Sheathing

zoom_out_map
zoom_out_map

View from Giant Road 12/13

Building F, E and D in the foreground from left to right
Lake Construction Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter