Lake ES -School Replacement Project
December 2024

Project Updates - December 2024
Construction Activity
Building E and F (Kindergarten Wings)
- Framing Exterior Walls
- Placing Roof Joists
- Installing Building Sheathing
Building D (Cafeteria)
- Preparation and Pouring Concrete Building Pad
- Begin Framing
Project Overview
- Project Scope: The primary purpose of this project is to replace the school campus. Campus will be occupied during the duration of this project. The project has two main construction phases. The first phase included new buildings and site work on the East half of the campus and the second phase will include new buildings and remaining site work on the West half of the campus. Project design started in August 2021 and the first phase of construction is complete. Phase 2 is scheduled through Fall 2025. This project is an investment in our community through the use of taxpayer bond dollars.
- Architect: Quattrocchi Kwok Architects - QKA
- Anticipated Completion: Fall 2025
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Sign up here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Installing Roof Joists
View from Giant Road 11/15
Building F, E and D in the foreground from left to right