Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE
District Wide Boiler Replacement
Replacement of aged boilers, feeder tanks, and electrical components as required
Awarded Contract Amount: $3,785,100.00 - This is for all boiler replacements
Paid to Date: $2,898,075.00
Renaissance @ Rand
Project Status: March 13, 2026
Project Completion: 83% complete
Current Status: Boiler feed unit install is currently ongoing
Upcoming Milestones: Rear exhaust dampers final installation
George Inness
Project Status: March 13, 2026
Project Completion: 88% complete
Current Status: Boiler feed unit is currently being connected
Upcoming Milestones: Final electrical is completed for programming and 2nd boiler Start up
Bradford Elementary
Project Status: March 13, 2026
Project Completion: 84% complete
Current Status: Boiler feed unit hook-up is ongoing
Upcoming Milestones: Final electrical to be scheduled
Watchung Elementary
Project Status: March 13, 2026
Project Completion: 85% complete
Current Status: Rear exhaust dampers are being installed
Upcoming Milestones: Final electrical is completed for programming and 2nd boiler Start up
Edgemont Elementary
Project Status: March 13, 2026
Project Completion: 84% complete
Current Status: Both boilers as well as vacuum pump install is nearing completion
Upcoming Milestones: Boiler feed unit is currently being piped and final electrical to be scheduled
Northeast Elementary
Project Status: March 13, 2026
Project Completion: 86% complete
Current Status: Installing rear exhaust damper on boiler #2
Upcoming Milestones: Complete rear exhaust damper