Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE

District Wide Boiler Replacement

Replacement of aged boilers, feeder tanks, and electrical components as required

Awarded Contract Amount: $3,785,100.00 - This is for all boiler replacements
Paid to Date: $2,898,075.00

Renaissance @ Rand Renaissance @ Rand

Project Status: March 13, 2026

Project Completion: 83% complete

Current Status: Boiler feed unit install is currently ongoing

Upcoming Milestones: Rear exhaust dampers final installation

User uploaded image
zoom_out_map Show in original size

George Inness George Inness

Project Status: March 13, 2026

Project Completion: 88% complete

Current Status: Boiler feed unit is currently being connected

Upcoming Milestones: Final electrical is completed for programming and 2nd boiler Start up

User uploaded image
zoom_out_map Show in original size

Bradford Elementary Bradford Elementary

Project Status: March 13, 2026

Project Completion: 84% complete

Current Status: Boiler feed unit hook-up is ongoing

Upcoming Milestones: Final electrical to be scheduled

User uploaded image
zoom_out_map Show in original size

Watchung Elementary Watchung Elementary

Project Status: March 13, 2026

Project Completion: 85% complete

Current Status: Rear exhaust dampers are being installed

Upcoming Milestones: Final electrical is completed for programming and 2nd boiler Start up

User uploaded image
zoom_out_map Show in original size

Edgemont Elementary Edgemont Elementary

Project Status: March 13, 2026

Project Completion: 84% complete

Current Status: Both boilers as well as vacuum pump install is nearing completion

Upcoming Milestones: Boiler feed unit is currently being piped and final electrical to be scheduled

User uploaded image
zoom_out_map Show in original size

Northeast Elementary Northeast Elementary

Project Status: March 13, 2026

Project Completion: 86% complete

Current Status: Installing rear exhaust damper on boiler #2

Upcoming Milestones: Complete rear exhaust damper

User uploaded image
zoom_out_map Show in original size

Newsletters Updates

November of 2022, in a historic show of unity, more than 80% of town voters backed the $188 million Bond Referendum to repair and modernize Montclair Public Schools' long-neglected buildings and decaying infrastructure (11 schools and the administration building constructed more than 99 years ago on average).

launch montclair.k12.nj.us
User uploaded image
zoom_out_map Show in original size
Conor O'Brien- Principal
Legacy Construction Management
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter