SHANNON ES - MPR Project
March 2025

Project Updates - March 2025
Construction Activity
- Fire sprinkler lines are installed and framing is mostly complete
- Scaffolding has been installed to prepare the building for installing weather barrier systems, lath, and stucco
- Roof membrane has been installed. Flashing and placement of rooftop equipment will begin this month
Project Overview
- Project Scope: The primary purpose of this project is to build a new multi-purpose room with a dining area, stage, and food services kitchen, servery, and support spaces. After the completion of the new building, the existing cafeteria portable will be removed. The project will include roll-up doors to support connection to the exterior, landscaping around the building, and infrastructure for a new garden. This project is an investment in our community through the use of taxpayer bond dollars.
- Architect: Hamilton + Aitken Architects
- Anticipated Completion: Fall/Winter 2025
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Sign up here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Interior Image
Preparing to install door and window frames