Activities This Month

  • The new domestic water line tie-in and testing is successfully completed
  • Significant progress was made on the storm drain system, including installation on the south and east sides of the site, along with installation of manholes
  • Finalize the subgrade preparation of the building pad
  • The new fire water line installation and tie-in is in progress
User uploaded image
zoom_out_map

Activities Next Month

  • We will be completing the utility make ready phase of the new classroom building

  • Pier drilling for the foundation of the new building will begin

Project Overview Project Overview

User uploaded image
zoom_out_map Show in original size

The Richmond High School Modernization project involves demolishing a portion of the classroom building to make way for a new two-story building along 23rd Street. The remaining classroom section will be updated, including the installation of new windows. The large gym and the 600 Buildings will receive a refresh.

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
User uploaded image
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.



Interested in serving? Apply here: bit.ly/CBOCWCCUSD23

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
RHS Modernization Project Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close
Powered by