Our gym is done! We once again have full use of our gym/cafeteria.


Our East Wing (C) is nearing completion. Once complete, we will move the four classrooms currently in the Middle Wing (B) into Wing C.


This move affects four classrooms:


  • 3rd grade
  • 4th grade
  • 5th grade
  • Music



Moving classrooms mid year is a huge undertaking. Our goal is to minimize impact on students + families. I'm working closely with facilities + our staff to ensure a safe, efficient move.


Once Wing B is emptied, construction will begin there + continue through Winter Break.

Dear Walterville Families,


As we prepare to welcome students back, I wanted to share important updates about the structural improvement work underway at Walterville Elementary.


Our school is one of several Springfield Public Schools buildings receiving structural improvements this year as part of work required to maintain the District's full property insurance coverage. The work primarily involves reinforcing structural beams and trusses in portions of the building.


I want to reassure you, Walterville Elementary remains safe and will open for school as scheduled. Students will see some changes to their normal routines while construction is underway, particularly involving classrooms, the gym, and meal spaces. These adjustments are temporary and will allow school to continue while crews complete the work.


Because of the scope of the project, construction will continue into the school year. Work is being completed in phases to minimize the number of classrooms and spaces affected at any one time.


Here is what families can expect as school begins:

  • Classrooms: Work on the first classroom wing (rooms 1-4) has been completed. Work on rooms 9-12 is underway. Construction will move through additional classroom areas in phases throughout the fall. As work moves from one area to another, some classrooms will temporarily relocate. District and school staff will handle those moves and work to make each transition as smooth as possible for students.

  • Gym and meals: Structural work is underway in the gym and is expected to be finished by the end of September. While crews complete this work, PE activities and student eating spaces will shift outdoors (as weather permits) or to classrooms.

  • School spaces: To preserve classrooms and student services during construction, some spaces are being temporarily repurposed or consolidated.

  • Construction areas: Active construction areas will be separated from students and staff. Families may notice fencing, construction materials and a storage container on portions of the campus.

  • Schedule: Work will continue in phases throughout the fall. Construction schedules can change as work progresses, so we will keep families informed as crews move to different areas of the school.


The project includes several methods of reinforcing the building's structural system, including steel reinforcement, cables, and epoxy applications. I am in close contact with the construction team, as well as District staff who are helping coordinate and oversee the construction.


We know construction during the school year will require some flexibility from our students, staff, and families. Our goal is to keep Walterville operating as normally as possible while completing this critical work. Families do not need to make any changes to their normal back-to-school plans because of the construction. I will continue to provide updates throughout the project, particularly when work moves into a new area or results in changes to students' normal routines.


Thank you for your patience and flexibility as we complete these improvements and get ready for a great school year at Walterville Elementary. Please do not hesitate to reach out to me with any questions.