Lake ES -School Replacement Project
October 2025

Project Updates - October 2025
Construction Activity
Building D (Cafeteria)
- October: Completed and tested building systems, finished wood flooring on the stage, and installed kitchen equipment.
- November: Cafeteria building will open for staff and student use.
Playground and Site
- November: Final touches are being completed on the staff parking lot, blacktop, and playground for a November opening!
- December: Turf, walking path, and garden area are under construction, with a projected opening in December.
Project Overview
Project Scope: This project will replace the school campus, which will remain occupied throughout construction. It represents an investment in our community using taxpayer bond dollars.
The project is divided into two main construction phases. Design began in August 2021. Phase 1 included new buildings and site work on the east half of the campus and was completed in Fall 2024. Phase 2 will focus on new buildings and remaining site work on the west half of the campus, scheduled for completion in Fall 2025.
Anticipated Completion: Winter 2025
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23