Dear Little Ferry School Community,
As we plan for the return of our students for a new school year, we are just as excited to share an update on the construction of Liberty Middle School and progress made over the summer. Since the community’s support of our bond referendum in March 2024, the district has taken significant steps toward building for the future of Little Ferry and the students we serve.
Additional Funding
First, on behalf of the Board of Education and district administration, I am proud to announce that Little Ferry Public Schools has received an additional $2.5 million to offset the local share of the project costs. We promised from the beginning that we would remain committed to working with Mayor Mauro Raguseo, State Sen. Joe Lagana, and Assembly Members Lisa Swain and Chris Tully in seeking additional opportunities for more funding toward this project.
This $2.5 million is in addition to the $5 million in initial funding we received in 2024 and the $7.75 million we received in summer 2025, bringing our cumulative total of additional funding to $15.25 million toward the $38 million project.
Progress Toward Completion
I also am happy to report that the building is 50% complete, and the closure of its exterior is reaching the final stage. Systems are in place and being connected and prepared for operation, and interior work is well underway. Despite some delays due to severe winter weather, we are still on track to have the new school ready to open in 2027.
Stay tuned for the next milestone on the progress meter!
To see a detailed list of the work in progress, please check this page of our website.