October 2026

Stege Rebuild Project October 2026
Stege RebuildProjectOctober 2026

October 2026 - Project Updates October 2026 - Project Updates

User uploaded image
zoom_out_map

Activities Next Month

  • Rough grading at drive isles and play area
  • Installation of underground electrical
  • Lime/cement treatment of soils at remaining site (building pads completed last month)
  • Continue utility improvements in the public right of way
  • Excavation of building foundations
  • Begin installation of foundation rebar
User uploaded image
zoom_out_map

Activities This Month

  • Continue building foundation excavations and rebar installation
  • Start pouring concrete building foundations
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

Project Summary

The Stege campus rebuild will replace existing buildings with a new site layout. Students are temporarily located at DeJean Middle School.
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
User uploaded image
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.


Interested in serving? Apply here: bit.ly/CBOCWCCUSD23

User uploaded image
zoom_out_map
User uploaded image
zoom_out_map
Stege ES Rebuild Project Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close
Powered by