RHS Modernization Project
October 2025

October 2025 - Construction Update
Activities This Month
- New Welcome Center OPENS on north side of campus
- Mobilization and installation of construction fencing around the main Phase 1 site
- Demolition of concrete and asphalt paving
Thank You!
Thank you to all who came out for the Phase 1 Ground Breaking ceremony. We enjoyed celebrating with the Richmond High Band and the cheer team!
Project Overview
Project Scope:
Richmond High School Modernization involves demolishing part of the classroom building to construct a new two-story building along 23rd Street. The remaining classroom section will be updated, including new windows, while the large gym and 600 Buildings will receive a refresh.
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Interested in serving? Apply here: bit.ly/CBOCWCCUSD23
Construction Fencing
Along 23rd Street
Parking Lot
Demolition of asphalt