remove_red_eye 843
Logo

Stege Rebuild Project

June 2025

Stege Rebuild Project June 2025
Stege RebuildProjectJune 2025

June 2025 - Design Development June 2025 - Design Development

zoom_out_map

Project Update

The Stege project will enter the Demolition Phase within the next few weeks. The Demolition contract has been completed and the contractor is preparing for mobilization. Expect to see exciting activity on the project site in the next few weeks.

The Design process has progressed beyond Schematic Design and we have reached the Design Development phase. This phase defines the details of the buildings. Input on the design was gathered in focus groups, parent and community meetings. The Maintenance & Operations staff will review the drawings the week of 6/09/2025.

In parallel, we are working with the City on approval of site layout and utility tie-in locations.

zoom_out_map
zoom_out_map
zoom_out_map
Project Website
zoom_out_map

Project Summary

This project will replace the existing school buildings and provide a new site design. The Stege campus rebuild project is in design. The school has been temporarily relocated to DeJean Middle School campus site until construction is complete. Demolition of the campus is scheduled for this spring/summer, and completion of the rebuild project is anticipated for Fall 2027.
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.


Sign up here: bit.ly/CBOCWCCUSD23

SES Modernization Project Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close
Powered by