Montclair Public Schools

September 16, 2024

Montclair Public Schools  September 16, 2024
MontclairPublic Schools September 16, 2024

Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE

District Wide Boiler Replacement

Replacement of aged boilers, feeder tanks, and electrical components as required

Awarded Contract Amount: $3,785,100.00 - This is for all boiler replacements
Paid to Date: $2,898,075.00

Renaissance @ Rand Renaissance @ Rand

Project Status: February 13, 2026

Project Completion: 77% complete

Current Status: Boiler #1 is complete; Boiler #2 is nearing completion

Upcoming Milestones: Boiler feed unit install to be completed next week. Rear exhaust dampers final installation and wiring still open

User uploaded image
zoom_out_map Show in original size

George Inness George Inness

Project Status: February 13, 2026

Project Completion: 82% complete

Current Status: Boilers #1 and #2 are installed, pending rear exhaust dampers and wiring

Upcoming Milestones: Boiler feed unit installation to be completed

User uploaded image
zoom_out_map Show in original size

Bradford Elementary Bradford Elementary

Project Status: February 13, 2026

Project Completion: 79% complete

Current Status: Boiler #1 is complete; Boiler #2 is nearing completion

Upcoming Milestones: Boiler feed unit install to be completed. Final electrical will be scheduled after Boiler #2 is fully plumbed in.

User uploaded image
zoom_out_map Show in original size

Watchung Elementary Watchung Elementary

Project Status: February 13, 2026

Project Completion: 80% complete

Current Status: Boilers #1 and #2 are complete except for insulation

Upcoming Milestones: Rear exhaust damper final installation and wiring to be completed. Final electrical is completed for programming

User uploaded image
zoom_out_map Show in original size

Edgemont Elementary Edgemont Elementary

Project Status: February 13, 2026

Project Completion: 78% complete

Current Status: Boiler 1 is complete, Boiler #2 is nearing completion

Upcoming Milestones: Vacuum pump is ready to be set in position, new pads for boiler feed unit is in place and feed unit needs to be piped in

User uploaded image
zoom_out_map Show in original size

Northeast Elementary Northeast Elementary

Project Status: February 13, 2026

Project Completion: 80% complete

Current Status: Both boilers are installed

Upcoming Milestones: Insulation and rear exhaust damper are being installed

User uploaded image
zoom_out_map Show in original size

Newsletters Updates

November of 2022, in a historic show of unity, more than 80% of town voters backed the $188 million Bond Referendum to repair and modernize Montclair Public Schools' long-neglected buildings and decaying infrastructure (11 schools and the administration building constructed more than 99 years ago on average).

launch montclair.k12.nj.us
User uploaded image
zoom_out_map Show in original size
Conor O'Brien- Principal
Legacy Construction Management
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter