Montclair Public Schools
September 16, 2024
Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE
District Wide Boiler Replacement
Replacement of aged boilers, feeder tanks, and electrical components as required
Awarded Contract Amount: $3,785,100.00 - This is for all boiler replacements
Paid to Date: $2,898,075.00
Renaissance @ Rand
Project Status: February 13, 2026
Project Completion: 77% complete
Current Status: Boiler #1 is complete; Boiler #2 is nearing completion
Upcoming Milestones: Boiler feed unit install to be completed next week. Rear exhaust dampers final installation and wiring still open
George Inness
Project Status: February 13, 2026
Project Completion: 82% complete
Current Status: Boilers #1 and #2 are installed, pending rear exhaust dampers and wiring
Upcoming Milestones: Boiler feed unit installation to be completed
Bradford Elementary
Project Status: February 13, 2026
Project Completion: 79% complete
Current Status: Boiler #1 is complete; Boiler #2 is nearing completion
Upcoming Milestones: Boiler feed unit install to be completed. Final electrical will be scheduled after Boiler #2 is fully plumbed in.
Watchung Elementary
Project Status: February 13, 2026
Project Completion: 80% complete
Current Status: Boilers #1 and #2 are complete except for insulation
Upcoming Milestones: Rear exhaust damper final installation and wiring to be completed. Final electrical is completed for programming
Edgemont Elementary
Project Status: February 13, 2026
Project Completion: 78% complete
Current Status: Boiler 1 is complete, Boiler #2 is nearing completion
Upcoming Milestones: Vacuum pump is ready to be set in position, new pads for boiler feed unit is in place and feed unit needs to be piped in
Northeast Elementary
Project Status: February 13, 2026
Project Completion: 80% complete
Current Status: Both boilers are installed
Upcoming Milestones: Insulation and rear exhaust damper are being installed