D28 Board Update: March 2026

Meadowbrook Gym Construction Nears Completion

D28 Board Update: March 2026 Meadowbrook Gym Construction Nears Completion
D28 Board Update:March 2026Meadowbrook Gym Construction Nears Completion

March 12, 2026

Meadowbrook Gym Construction Nears Completion Meadowbrook Gym Construction Nears Completion

Build 28: Meadowbrook Gymnasium Interior (Jan. 8 - March 11, 2026)
User uploaded image
zoom_out_map

During his Superintendent's Report at the March 10 District 28 Board of Education meeting, Dr. Pearson shared an update on the district's $94.9 million Build 28 initiative, made possible by the community's support last spring.

Construction is nearing completion on the new Meadowbrook gymnasium. This week, crews are installing the gym floor. It is anticipated that students and staff will be able to start using the new gym shortly after spring break. Check out the latest time-lapse video by clicking the link above! Meanwhile, construction on the new Meadowbrook School, which will seamlessly attach to the new gym, is anticipated to begin in mid to late April.

Dr. Pearson also shared new schematic design renderings (see below) of the projects at Greenbriar and Westmoor, which go out to bid on March 12. The Board is anticipated to approve a contractor for those projects at its April meeting. Major construction at each building is anticipated to begin this summer. Northbrook Junior High is expected to go to bid in the fall. By staggering the bid process, the district anticipates maximizing the amount of work that can be completed at all schools.

Greenbriar Schematic Design Renderings Greenbriar Schematic Design Renderings

User uploaded image
zoom_out_map

New Greenbriar cafetorium (cafeteria/auditorium)

User uploaded image
zoom_out_map

New Greenbriar courtyard

User uploaded image
zoom_out_map

Exterior of the Greenbriar cafetorium from the west side of the building

Westmoor Schematic Design Renderings Westmoor Schematic Design Renderings

User uploaded image
zoom_out_map

New Westmoor cafetorium

User uploaded image
zoom_out_map

Corridor leading to the new Westmoor cafetorium

User uploaded image
zoom_out_map

Corridor/multipurpose learning space connecting the cafetorium to the current building

Build 28 Projected Construction Timeline

  • March 2026: Meadowbrook gymnasium completed & construction of the new Meadowbrook School begins
  • June 2026: Westmoor & Greenbriar construction begins
  • Nov. 2026 - March 2027: NBJH construction begins
  • Feb. - April 2027: Westmoor & Greenbriar Phase 1 construction completed
  • August 2027: New Meadowbrook School completed
  • February 2028: Greenbriar Phase 2 completed
  • August 2028: NBJH construction completed
VISIT THE BUILD 28 WEBSITE

AI in D28: Learning First, Technology Second AI in D28: Learning First, Technology Second

User uploaded image
zoom_out_map

At the March 10 Board meeting, Director of Technology Maria Stavropoulos shared a presentation about the district's phased approach to artificial intelligence (AI) in schools.

Guided by the principle of “learning first, technology second,” the district formed an AI Task Force last summer, comprised of teachers, instructional leaders, and technology staff, to explore how AI can responsibly support teaching and learning. Since then, the district has focused on building staff understanding, establishing clear guidance for the use of approved AI tools, and ensuring strong privacy protections for students. NBJH student focus groups also provided valuable insight, with students emphasizing the importance of maintaining human interaction in classrooms and using AI as a support—not a replacement—for teachers.

District 28 will continue this work through a phased plan that includes staff learning, student voice, family engagement, and long-term planning. Upcoming efforts will include parent information sessions and opportunities for community feedback as the district develops responsible and transparent practices for AI use.

Board Approves New Director of Student Services Board Approves New Director of Student Services

Photo of Dr. Apgar and Board President Mara Silver-Shack
zoom_out_map

At the March 10 Board meeting, the Board approved Dr. Eric Apgar as the district's new Director of Student Services. He will begin in his new role on July 1, replacing Dr. Kelly Sculles, who will be the new Executive Director of the Mid-Valley Special Education Cooperative.


Dr. Apgar comes to District 28 from Round Lake Area Schools 116, where he currently works as the Assistant Superintendent/Executive Director of Student Services. He previously worked as the Director of Guidance at Carl Sandburg High School and as the Director of Student Personnel Services at Maine Township High School West. He began his career as a School Psychologist with Community High School District 155.


Dr. Apgar earned his doctorate in Educational Leadership from Concordia University. He also holds two master's degrees, one in Educational Leadership from Northern Illinois University and one in Counseling Psychology from Loyola University. He holds a bachelor's degree in Psychology from Evangel University. (Photo: Board President Mara Silver-Schack and Dr. Apgar)

District Receives State Grant to Replace Rooftop Units at Westmoor District Receives State Grant to Replace Rooftop Units at Westmoor

At the March 10 Board meeting, the Board approved replacing two rooftop units at Westmoor School, which have exceeded their operating lifespan. The total cost of the project is $118,760; however, the district's total cost will be $68,760, thanks to a $50,000 state grant. The School Maintenance Project Grant (SMPG) is a dollar-for-dollar state matching grant program that provides awards up to $50,000 to grantees exclusively for the maintenance or upkeep of buildings or structures for educational purposes. This marks the fifth time District 28 has been awarded $50,000 through this grant.

Board Approves New Educator Hire Board Approves New Educator Hire

At the March 10 Board meeting, the Board approved the appointment of the following certified personnel for the 2026-27 school year:


Brendan Frank, Band Director (District-wide)

Mr. Frank earned a master's degree in Music Education from Eastern Illinois University. He currently works as a Music Teacher in Antioch School District 34.

Want to Know More? Want to Know More?

Livestream/Archive Video

The Board of Education meetings are live-streamed on the District 28's YouTube Channel. The live streams are also archived for later viewing.


Next Meeting is on April 28

The Board of Education's next regular meeting is at 7 p.m. on April 28 in the HOH Community Room at the District Office, 1475 Maple Ave., Northbrook.

Collage of all Board member headshots with district logo in the upper left hand corner
zoom_out_map Show in original size
VISIT THE BOARD OF EDUCATION WEBPAGE
Northbrook School District 28
https://www.northbrook28.net/
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter