Hercules CNP

December 2024

Hercules CNP December 2024
HerculesCNPDecember 2024

Project Updates - December 2024 Project Updates - December 2024

zoom_out_map

Construction Completed Last Month

  • Completed plastering the outdoor patio canopies
  • Began roofing on the patio canopies
  • Installed appliances
  • Placed turf in the amphitheater
zoom_out_map

Construction Work Planned for This Month

  • Complete site clean up, irrigation and landscaping
  • Finish installing concrete sidewalks and patios
  • Complete punch list items

Project Overview Project Overview

  • Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
  • Architect: DSK Architects
  • Contractor: Soltek Pacific Construction
  • Anticipated Completion: Fall / Winter 2024
zoom_out_map

Join the CBOC!

We are accepting applications to join the Citizens' Bond Oversight Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.


Sign up here: bit.ly/CBOCWCCUSD23

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
zoom_out_map

Starting the Planting and Installed Guardrails

zoom_out_map
zoom_out_map

Patio Canopies

Hercules Construction Newsletter
WCCUSD Facilities Planning & Construction
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter