NTCSD Capital Project Update

Volume 4, April 2026

NTCSD CapitalProject UpdateVolume 4, April 2026

Capital Project Overview Capital Project Overview

The District's 2024 Capital Improvement Project is well underway. Continued planning has been made since the District's last capital project update with the goal of no disruptions to student learning and achievement to start the 2026-2027 school year.


The goal of this Smore and subsequent newsletters is to keep the NTCSD community and staff aware of the exciting capital project work the district has going on as well as insights into future plans as they develop.

Phase 1A Phase 1A

Phase 1A construction has concluded and all final costs reports have been submitted to the State Education Department before the start of the new calendar year. This will ensure that the district receives accelerated state Building Aid payments in the 2026-2027 school year.

Phase 1B Phase 1B

Capital Project Construction Update: Work Underway

Since the last Smore update in January, the District has engaged in strategic planning and mobilizing with contractors for phase 1B.


While light construction officially began over winter recess for Phase 1B with the refinishing of the Drake gymnasium floor, much more complicated work is slated to begin this summer. During the most recent spring recess period, the Ohio gymnasium floor, high school pool pump, and the Transportation Center began their scheduled upgrades. The Transportation Center is anticipated to finish construction by the middle of August. A temporary office for any community members needing to communicate with the department has been established in a work trailer behind the building next to the bus parking lot. Photos of the current scope of work have been inserted below.


Phase 1B Highlights

Phase 1B will bring meaningful improvements to schools and facilities across the District, including:


  • Energy-efficient LED school signage

  • Refinished gymnasium floors at K–3 elementary schools

  • Cafetorium and auditorium renovations at K–6 elementary schools

  • Energy-efficient window replacements at Spruce and Drake

  • Classroom cabinet and filtered sink replacements at K–3 buildings

  • Interior renovations at the Transportation Center

  • A new secure front-door vestibule at the high school

  • Energy-efficient electrical, HVAC, and mechanical upgrades throughout K–6 buildings


Summer 2026 Work

During the summer months, heavy construction will be taking place throughout the district. The planned scope of work includes:


Drake - Finishing the remaining roof replacements, window replacements

Ohio - Classroom cabinet and sink replacements

Spruce - Cabinet, sink, and window replacements, as well as gymnasium floor refinishing

NTI - Electrical upgrades

MS/HS Campus- Secure attendance office vestibule as well as pool mechanical upgrades


Fall 2026 Work and Beyond

Construction will continue throughout the 2026–2027 school year as part of Phase 1B. During the fall and winter months, the Spruce auditorium will undergo significant renovations. Remaining construction work at Drake and Spruce is anticipated to begin during the spring 2027 recess period and continue through the summer.

User uploaded image
zoom_out_map

Ohio Elementary Gymnasium - Before Renovation

User uploaded image
zoom_out_map

Ohio Elementary Gymnasium - During Renovation

User uploaded image
zoom_out_map

Ohio Elementary Gymnasium - During Renovation

User uploaded image
zoom_out_map

Ohio Elementary Gymnasium - During Renovation

User uploaded image
zoom_out_map

Ohio Elementary Gymnasium - During Renovation

User uploaded image
zoom_out_map

Ohio Elementary Gymnasium - After Renovations

Ohio Elementary Gymnasium - After Renovations Ohio Elementary Gymnasium - After Renovations

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

High School Pool Pump Area - Before Renovation

User uploaded image
zoom_out_map

High School Pool Pump Area - During Renovation

User uploaded image
zoom_out_map

High School Pool New Supply Cabinet - After Renovation

User uploaded image
zoom_out_map

Transportation Center - Before Renovation

User uploaded image
zoom_out_map

Transportation Center - Before Renovation

User uploaded image
zoom_out_map

Transportation Center - Before Renovation

User uploaded image
zoom_out_map

Transportation Center - During Renovation

User uploaded image
zoom_out_map

Transportation Center - During Renovation

User uploaded image
zoom_out_map

Transportation Center - During Renovation

User uploaded image
zoom_out_map

Transportation Center - During Renovation

User uploaded image
zoom_out_map

Transportation Center - During Renovation

User uploaded image
zoom_out_map

Transportation Center - During Renovation

Phase 2 Phase 2

Capital Project Construction Update: Designs Submitted

Phase 2 will undoubtedly be the most complex portion of the capital project as it primarily focuses on classroom redesign at the high school and energy-efficient window replacement at NTMS. The architects and construction managers have held multiple meetings with the district and instructional leaders. Phase 2 construction is anticipated to begin during the spring of 2027. Specifically, this part of the project will likely include:


- Energy-efficient mechanical and HVAC upgrades at the middle school and high school.

- FACS, art, science, and music room renovations at the high school.

District Proposes Future Capital Improvement Project (May 2026 Budget Vote) District Proposes Future Capital Improvement Project (May 2026 Budget Vote)

User uploaded image
zoom_out_map

At the January 7th, February 4th, and March 4th Board of Education meetings, district administration along with the district's architect, construction manager firm, and fiscal advisor presented an series of presentations regarding of a potential future capital improvement project.


This opportunity is made possible by the successful completion and payoff of prior capital project work, along with the availability of district capital reserves that are legally dedicated for capital improvements. From a financial standpoint, the proposed project would be structured to result in no additional tax levy impact for district residents. All project costs would be funded exclusively through a combination of New York State Building Aid and district capital reserves, which by law may only be used for capital projects after community project approval.


If ultimately approved by the community at the upcoming May budget vote, the project would be implemented over multiple years, with work extending through the 2030–2031 school year.


January 7th Capital Project Presentation Link

February 4th Capital Project Presentation Link

March 4th Architect & Construction Manager Presentation Link

March 4th Fiscal Advisor Presentation Link

March 4th Inclusive Playground Presentation Link


*Please scan the QR code for community feedback and an opportunity to ask questions regarding the proposed Capital Improvement Project. A comprehensive Question & Answer document will be constructed based on feedback prior to the community-wide vote.

Yearly Capital Outlay Project: Annual Facility Improvements Yearly Capital Outlay Project: Annual Facility Improvements

Each year, pending voter approval of the school budget, the District is permitted by law to complete a $100,000 Capital Outlay Project. These projects are the “express lane” version of capital improvements allowing the District to complete targeted facility upgrades efficiently in one calendar year, without the time and scale required for larger, multi-year capital projects. These targeted improvement projects help ensure District facilities continue to be safe, functional, and well maintained.


In 2023–2024 and 2024–2025, Capital Outlay Projects included select door replacements at NTMS and NTHS, enhancing both safety and functionality.


The 2025–2026 Capital Outlay Project focused on the installation of playground fencing at K–3 elementary schools. These fences provide an added safety barrier between playground areas and adjacent streets, while still allowing community access to the playgrounds during non-school hours. All fencing has now been completed and is ready for students and families to enjoy.


Looking ahead, and pending a successful budget vote this spring, the District plans for the 2026–2027 Capital Outlay Project to primarily focus on playground expansion at Drake as the top project priority.

Drake Elementary Playground Fence Drake Elementary Playground Fence

Drake Elementary Playground
zoom_out_map Show in original size

Ohio Elementary Playground Fence Ohio Elementary Playground Fence

Ohio Elementary Playground
zoom_out_map Show in original size

Spruce Elementary Playground Fence Spruce Elementary Playground Fence

Spruce Playground
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
Joshua Janese
Joshua is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter