NTCSD Capital Project Update
Volume 4, April 2026
Capital Project Overview
The District's 2024 Capital Improvement Project is well underway. Continued planning has been made since the District's last capital project update with the goal of no disruptions to student learning and achievement to start the 2026-2027 school year.
The goal of this Smore and subsequent newsletters is to keep the NTCSD community and staff aware of the exciting capital project work the district has going on as well as insights into future plans as they develop.
Phase 1A
Phase 1A construction has concluded and all final costs reports have been submitted to the State Education Department before the start of the new calendar year. This will ensure that the district receives accelerated state Building Aid payments in the 2026-2027 school year.
Phase 1B
Capital Project Construction Update: Work Underway
Since the last Smore update in January, the District has engaged in strategic planning and mobilizing with contractors for phase 1B.
While light construction officially began over winter recess for Phase 1B with the refinishing of the Drake gymnasium floor, much more complicated work is slated to begin this summer. During the most recent spring recess period, the Ohio gymnasium floor, high school pool pump, and the Transportation Center began their scheduled upgrades. The Transportation Center is anticipated to finish construction by the middle of August. A temporary office for any community members needing to communicate with the department has been established in a work trailer behind the building next to the bus parking lot. Photos of the current scope of work have been inserted below.
Phase 1B Highlights
Phase 1B will bring meaningful improvements to schools and facilities across the District, including:
-
Energy-efficient LED school signage
-
Refinished gymnasium floors at K–3 elementary schools
-
Cafetorium and auditorium renovations at K–6 elementary schools
-
Energy-efficient window replacements at Spruce and Drake
-
Classroom cabinet and filtered sink replacements at K–3 buildings
-
Interior renovations at the Transportation Center
-
A new secure front-door vestibule at the high school
-
Energy-efficient electrical, HVAC, and mechanical upgrades throughout K–6 buildings
Summer 2026 Work
During the summer months, heavy construction will be taking place throughout the district. The planned scope of work includes:
Drake - Finishing the remaining roof replacements, window replacements
Ohio - Classroom cabinet and sink replacements
Spruce - Cabinet, sink, and window replacements, as well as gymnasium floor refinishing
NTI - Electrical upgrades
MS/HS Campus- Secure attendance office vestibule as well as pool mechanical upgrades
Fall 2026 Work and Beyond
Construction will continue throughout the 2026–2027 school year as part of Phase 1B. During the fall and winter months, the Spruce auditorium will undergo significant renovations. Remaining construction work at Drake and Spruce is anticipated to begin during the spring 2027 recess period and continue through the summer.
Ohio Elementary Gymnasium - Before Renovation
Ohio Elementary Gymnasium - During Renovation
Ohio Elementary Gymnasium - During Renovation
Ohio Elementary Gymnasium - During Renovation
Ohio Elementary Gymnasium - During Renovation
Ohio Elementary Gymnasium - After Renovations
Ohio Elementary Gymnasium - After Renovations
High School Pool Pump Area - Before Renovation
High School Pool Pump Area - During Renovation
High School Pool New Supply Cabinet - After Renovation
Transportation Center - Before Renovation
Transportation Center - Before Renovation
Transportation Center - Before Renovation
Transportation Center - During Renovation
Transportation Center - During Renovation
Transportation Center - During Renovation
Transportation Center - During Renovation
Transportation Center - During Renovation
Transportation Center - During Renovation
Phase 2
Capital Project Construction Update: Designs Submitted
Phase 2 will undoubtedly be the most complex portion of the capital project as it primarily focuses on classroom redesign at the high school and energy-efficient window replacement at NTMS. The architects and construction managers have held multiple meetings with the district and instructional leaders. Phase 2 construction is anticipated to begin during the spring of 2027. Specifically, this part of the project will likely include:
- Energy-efficient mechanical and HVAC upgrades at the middle school and high school.
- FACS, art, science, and music room renovations at the high school.
District Proposes Future Capital Improvement Project (May 2026 Budget Vote)
At the January 7th, February 4th, and March 4th Board of Education meetings, district administration along with the district's architect, construction manager firm, and fiscal advisor presented an series of presentations regarding of a potential future capital improvement project.
This opportunity is made possible by the successful completion and payoff of prior capital project work, along with the availability of district capital reserves that are legally dedicated for capital improvements. From a financial standpoint, the proposed project would be structured to result in no additional tax levy impact for district residents. All project costs would be funded exclusively through a combination of New York State Building Aid and district capital reserves, which by law may only be used for capital projects after community project approval.
If ultimately approved by the community at the upcoming May budget vote, the project would be implemented over multiple years, with work extending through the 2030–2031 school year.
January 7th Capital Project Presentation Link
February 4th Capital Project Presentation Link
March 4th Architect & Construction Manager Presentation Link
March 4th Fiscal Advisor Presentation Link
March 4th Inclusive Playground Presentation Link
*Please scan the QR code for community feedback and an opportunity to ask questions regarding the proposed Capital Improvement Project. A comprehensive Question & Answer document will be constructed based on feedback prior to the community-wide vote.
Yearly Capital Outlay Project: Annual Facility Improvements
Each year, pending voter approval of the school budget, the District is permitted by law to complete a $100,000 Capital Outlay Project. These projects are the “express lane” version of capital improvements allowing the District to complete targeted facility upgrades efficiently in one calendar year, without the time and scale required for larger, multi-year capital projects. These targeted improvement projects help ensure District facilities continue to be safe, functional, and well maintained.
In 2023–2024 and 2024–2025, Capital Outlay Projects included select door replacements at NTMS and NTHS, enhancing both safety and functionality.
The 2025–2026 Capital Outlay Project focused on the installation of playground fencing at K–3 elementary schools. These fences provide an added safety barrier between playground areas and adjacent streets, while still allowing community access to the playgrounds during non-school hours. All fencing has now been completed and is ready for students and families to enjoy.
Looking ahead, and pending a successful budget vote this spring, the District plans for the 2026–2027 Capital Outlay Project to primarily focus on playground expansion at Drake as the top project priority.