Bond Update

August 2024

Bond UpdateAugust 2024
At the August Board meeting, MISD Executive Director of Facilities gave an update on the November 2022 Bond projects.

Audubon Elementary Audubon Elementary

Audubon Elementary opened on August 8 and welcomed new students! Thank you to the tax payers for supporting this new elementary school.

Intermediate #3 Intermediate #3

Intermediate #3 is ahead of schedule and is now estimated to be completed by November 2024. The school will open in August 2025.
zoom_out_map

Gymnasium

zoom_out_map

Library

zoom_out_map

Cafeteria

zoom_out_map

Kitchen

zoom_out_map

Classroom corridor

zoom_out_map

Classroom

Junior High #3 Junior High #3

The new junior high is on schedule to be completed in March or April of 2025. The current work happening includes exterior work and installation of windows. The construction site is waiting on permanet power which should be turned on in the next 30 days.
zoom_out_map

Fine arts wing

zoom_out_map

Classroom wing

zoom_out_map

Main corridor

zoom_out_map

Library

zoom_out_map

Classroom

zoom_out_map

Classroom corridor

zoom_out_map

East side and gym entrance

zoom_out_map

Field house and concession stand

CTE Projects and Ag Barn Updates CTE Projects and Ag Barn Updates

The CTE projects at both high schools (HVAC at MWHS and Health Sciences at MHS) are currently under construction. The exterior of MWHS is completed and MH is waiting on the metal building to arrive and to be set on the foundation. The estimated completion is by the end of 2024.


The Ag Barn renovations are currently underway. The construction should be complete by the September Ag Show.

zoom_out_map

MWHS CTE Building

zoom_out_map

MWHS CTE interior

zoom_out_map

Ag Barn concession stand

zoom_out_map

Ag Barn additions

zoom_out_map

Ag Barn lighting and fan upgrades

zoom_out_map

Ag Barn additions

NJROTC Renovations NJROTC Renovations

The NJROTC program is housed at the MHS campus for both high schools. The drawings are 95% completed and the project is expected to take 6 - 8 months.

zoom_out_map

Magnolia ISD

November 2022 Bond

Email: info@magnoliaisd.org
Website: www.magnoliaisd.org
Location: 31141 Nichols Sawmill Road, Magnolia, TX, USA
Phone: 281-356-3571
Facebook: https://www.facebook.com/MagnoliaISD

Magnolia ISD
Magnolia is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter