Project Updates - July 2023 Project Updates - July 2023

Summer Work - Site

Reminder: The front entrance to the school will be closed over the summer. Next school year the front drop-off areas will be back and operating similarly to this year.

zoom_out_map

Construction Completed Last Month

  • Classroom sinks and casework were removed
  • Installation of refrigerant lines, ductwork, and fan coil units
  • Demolition of the front sidewalk
  • Installation of underground utilities in the staff parking lot
  • Demolition of kindergarten restrooms

Upcoming Activities

  • Installation of accessible classroom sinks and casework
  • Installation of accessible restrooms in the kindergarten classrooms
  • Replacement of classroom door hardware
  • Installation of the branch selector boxes

Project Overview Project Overview

  • Project Scope: Improvements to site HVAC Systems, Electrical Infrastructure, and Accessibility including path of travel improvements and parking lot updates.
  • Architect: PBK Architects

  • Anticipated Completion: Spring 2024

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
zoom_out_map

Front Drop Off

Concrete formwork being installed

zoom_out_map
zoom_out_map

Staffing Parking Lot

Installation of underground utilities

Collins Critical Need Project Newsletter
WCCUSD Facilities Planning & Construction
Signature facebook Signature instagram
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter