Collins ES Critical Needs Project
July 2023

Project Updates - July 2023
Summer Work - Site
Reminder: The front entrance to the school will be closed over the summer. Next school year the front drop-off areas will be back and operating similarly to this year.
Construction Completed Last Month
- Classroom sinks and casework were removed
- Installation of refrigerant lines, ductwork, and fan coil units
- Demolition of the front sidewalk
- Installation of underground utilities in the staff parking lot
- Demolition of kindergarten restrooms
Upcoming Activities
- Installation of accessible classroom sinks and casework
- Installation of accessible restrooms in the kindergarten classrooms
- Replacement of classroom door hardware
- Installation of the branch selector boxes
Project Overview
- Project Scope: Improvements to site HVAC Systems, Electrical Infrastructure, and Accessibility including path of travel improvements and parking lot updates.
-
Architect: PBK Architects
Anticipated Completion: Spring 2024
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Front Drop Off
Concrete formwork being installed
Staffing Parking Lot
Installation of underground utilities