May 27, 2026

Bond Update

May 27, 2026 Bond Update
May 27, 2026Bond Update
User uploaded image
zoom_out_map Show in original size

WEEKLY ROUNDUP!🎯 WEEKLY ROUNDUP!🎯

User uploaded image
zoom_out_map Show in original size

As we close in on the last 5 days of school with students, the summer bond machine is red-lining the production meter! We will see and expansion shortly after students depart!


  • Paving on the new bus loop/drive may start as early as June 3! See impact area below (yellow line is paving area).
    • Should not impact student or parent car pool traffic


  • New Furniture for the middle and high schools will be delivered Mid-July

ON-GOING PROJECTS 📆 ON-GOING PROJECTS 📆

User uploaded image
zoom_out_map Show in original size

🚌BID PACKAGE 1B PAVING THE WAY!🚌 🚌BID PACKAGE 1B PAVING THE WAY!🚌

Phase 1 of BP1B Ushers in Access Drive and New Bus Lanes 🚌

🚌New Updates!🚌

Recent progress continues with the drive near the location of the baseball and softball fields, with crews beginning the installation of conduit for the light pole bases. Sidewalk areas have also advanced, with grading completed and concrete poured to support improved access around the fields. In addition, work was completed on the stone flared end section for the stormwater system, helping to support site drainage improvements.


Looking ahead, crews are expected to continue the electrical underground work for the pole bases. Final preparation for the asphalt base will also continue as the site moves closer to the next phase of paving work.


Other Information/Reminders

Bid Package 1B carried an overall budget of $6.2 million, with the selected bid coming in approximately $200,000 under budget at $5.9 million. The work will be completed in two phases: Phase 1 will begin and be completed during the summer of 2026, with Phase 2 scheduled for the summer of 2027.


Planning accomplished in the redesign of the traffic flow in and around the middle and high school buildings. Based on observation and feedback, we feel we have the best plan possible to address safety and flow concerns. A few notables:


  • Fully separate buses from carpool and staff traffic at both the middle and high schools
  • Reconfigure the carpool traffic routes at both the middle and high schools
  • Add needed parking in front of middle and high schools
  • Add a through drive east to west for bus traffic to move within our district
  • Open Holler Lane to all traffic coming in or out of the campus allowing for efficient flow
  • NOTE: the removal of 4 current tennis courts will be needed to facilitate the bus lane behind the building due to grade and utilities limitations. As a reminder, 12 new courts will be constructed south of the stadium in bid package 4.
User uploaded image
zoom_out_map

Running of Conduit for Light Pole Bases

User uploaded image
zoom_out_map

Stone at Flared End Section

User uploaded image
zoom_out_map

More Stone

User uploaded image
zoom_out_map

New Sidewalk Pour at Softball/Baseball Lot

User uploaded image
zoom_out_map

Forming up Sidewalk Pour

User uploaded image
zoom_out_map

Forming up Sidewalk Pour

BID PACKAGE 2A - MAINTENANCE & TRANSPORTATION🚌 BID PACKAGE 2A - MAINTENANCE & TRANSPORTATION🚌

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

New Updates! 🚌🎒🏫😍

Recent work on the Transportation and Maintenance Facility continues to show steady progress. Metal wall installation has been completed on the north side of the building, and exterior wall framing is ongoing in the administrative area. The underground plumbing inspection for the administrative area has been approved, allowing that portion of the work to continue moving forward. Crews have also started rough-ins for the bus charging stations and have begun trim-out work on the overhead doors.


Looking ahead, work is expected to continue with metal wall panel installation on the west side of the building, additional exterior framing on the east elevation of the administrative area, and continued underground plumbing work.


Great progress!!

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

Trim Out of Person Door Opening

User uploaded image
zoom_out_map

Bus Charging Stations Rough-Ins

User uploaded image
zoom_out_map

Plumbing Underground Rough-Ins

Summer Fun on Order!😎🔅 Summer Fun on Order!😎🔅

User uploaded image
zoom_out_map

Many Projects Coming Online!😮

This spring and summer, Mattawan Consolidated School will advance with major components of our ongoing $110M school construction bond project!


😎During the summer of 2026 we will partner with Great Lakes Furniture Supply to install new furniture at both the middle school and high school—including new teacher workstations, key program supports (choir risers/chairs, music stands, robotics/STEM workstations), and a substantial refresh of high school student classroom furniture—completed under budget so building leaders could secure all identified high-priority items.


😎Phase 1 of Bid Package 1B (Traffic Flow) will be underway this spring. This will involved the construction of a new bus lane southside of the middle/high school as well as an access drive between the middle school and ball diamonds. The entire project came in about $200,000 under the $6.2M budget at $5.9M. Phase 2 is scheduled for summer 2027 and will address parking and carpool/traffic flow on the North side of the middle and high schools.


😎Construction progress continues on the new Transportation & Maintenance Facility, with work moving forward again this summer.


😎Phase two of our stadium enhancement scheduled to begin in the Summer of 2026, will include the addition of a new sound system, as well as the completion of the home bleacher facing (top portion).


😎Construction documents will wrap up this June for the New Cafeteria and Main Office project at the middle school. The projects will go out for bid after this!

Archived Information Here!📂 Archived Information Here!📂

BP 2A Information BP 2A Information

Bid Package 2A - Site Work & Prep 🏢🚍🔧

Did you know?

  • Current Maintenance Building will be demolished to make room for Natatorium/Field House

  • Current Bus Barn will be maintained as a district storage facility

  • New building will serve as primary hub for both maintenance and transportation departments

  • Total Square Footage of new building: 24,554 sq ft

  • Building Highlights:

    • 4 drive through bus maintenance bays

    • Dedicated parts room, wood shop and machine shop

    • Dedicated, dehumidified district storage

    • Locker rooms

    • Kitchen

    • Training room/lounge

    • 4 offices with additional workstations for secretaries and maintenance staff

    • Building Receiving Loading Dock

    • 40 exterior bus parking spots

    • Secured employee parking

    • Exterior salt storage


General Information

Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker-and-shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.


This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.


Tree Removal/Replacement & Disc Golf Course

The disc golf course on the west side of the high school was recently removed to prepare for construction of the new transportation and maintenance facility, slated to begin this winter. Approximately nine baskets and several trees were removed, a step the district did not take lightly. We recognize how meaningful this wooded space and recreational area have been for students and neighbors, and we share the disappointment that comes with altering a natural setting. Our team is working carefully to limit environmental impact and is committed to thoughtful tree replacement as part of the project. We are also exploring possibilities for relocating the disc golf course—potentially off campus—so the community can continue to enjoy the game in a new setting.

User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map Show in original size

Classroom Furniture Update🪑🏫 Classroom Furniture Update🪑🏫

Installation set for Summer of 26! 🪑🏫🍎

During the summer of 2026, Mattawan Consolidated School will partner with Great Lakes Furniture Supply to install new furniture in both the middle school and high school. Updates will include new teacher workstations at both buildings and select supporting furniture at each building, including choir risers and chairs, music stands, robotics/STEM workstations. Additionally the high school will be receiving a substantial amount of new student classroom furniture. This project was completed under budget, enabling building leaders to secure all items identified as high priorities while enhancing learning and instructional environments districtwide.


Click on the link below for more details.

Bond Update with Furniture Detail

Construction Bid Packages Explained Construction Bid Packages Explained

User uploaded image
zoom_out_map Show in original size

Our Plan. Our Students. Our Future. Our Plan. Our Students. Our Future.

User uploaded image
zoom_out_map

Our focus revolves around five key objectives for the bond:


  1. Preserve existing assets
  2. Prioritize safety and security
  3. Provide future-focused academic and extracurricular experiences for our students
  4. Enhance infrastructure
  5. Demonstrate fiscal responsibility


Safety & Security:

  • Addressing traffic congestion, lack of parking spaces, and separation of traffic and busing through enhancements
  • Replacement of outdated, unreliable security equipment at each building

Transportation:

  • Continued replacement of an aging bus fleet

Academic Learning Spaces + Experience:

  • Replacement of original, aged classroom equipment and furniture at middle and high schools
  • Updates to original, outdated science areas at middle and high schools (excluding the newly renovated portions) to ensure students have state of the art experiences.

Fine Arts:

  • Upgrades to lighting and media equipment at the high school auditorium

Infrastructure:

  • Replacement of original, outdated lockers, bathrooms, various ceilings, and lighting at middle and high schools
  • Renovations to high school weight room including expansion to address overcrowding and scheduling issues for student-athletes and physical education courses
  • Upgrade of aged building controls at middle and high schools (water, fire, HVAC, etc.) to provide the most efficient and safe environmental controls
  • Addition of cooling to main gymnasiums at the high school

Student Athletic Experience:

  • Renovation of aged high school locker rooms
  • Renovation of the high school stadium, including artificial turf, new entryways, expanded concessions
  • New high school track - the current track is backwards and nearly unusable in the current condition
  • Upgrades to baseball and softball fields
  • Construction of a new multi-use turf field (soccer, lacrosse, football)
  • Maintenance of existing practice fields; addition of a new outdoor practice space

Other Construction:

  • Addressing overcrowding in the current Middle School cafeteria
  • Replacement of aged, quickly deteriorating tennis courts
  • Replacement of aged transportation building and maintenance building
  • Construction of a fieldhouse facility for indoor practice teams/band to address lack of 12-month practice space; available for community use
  • Construction of a student/community pool
User uploaded image
zoom_out_map Show in original size
User uploaded image
zoom_out_map

Construction Bid Packages Explained

The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.


2024

  • Summer 2024

    • ✅COMPLETE Owner Direct – Replace Existing Soccer Lights

    • ✅COMPLETE Owner Direct – Technology Infrastructure (Switches, Wireless, HS Fiber Upgrades)

  • Fall 2024

    • ✅COMPLETE Owner Direct – Student Device Replacement Phase 1


Winter 2025

  • ✅COMPLETE Owner Direct – Student Device Replacement Phase 2


2025

  • March – August 2025

    • ✅COMPLETE - Bid Package 1A – Football Stadium: Inner Scope

  • Summer 2025

    • ✅COMPLETE- Bid Package 1C – Baseball & Softball Field Improvements

    • ✅COMPLETE Bid Package 1D – HS Replace Fire Alarm System

    • ✅COMPLETE Bid Package 1E – HS Carpet Replacement

  • Fall 2025

    • ✅UNDERWAY- Bid Package 1F – HS Gymnasium Cooling

    • ✅SOURCING MATERIALS Owner Direct – Auditorium (Band Shell, Pit Section, Lighting, Stage Floor, A/V, Curtain)

  • Nov 2025 – Oct 2026

    • ✅UNDERWAY Bid Package 2 – Transportation & Maintenance Facility


2026

  • March – September 2026

    • ✅PROJECT UNDERWAY - Bid Package 1B – Campus Traffic Flow

  • Sept 2026 – March 2028

    • ✅DESIGN PHASE UNDERWAY - Bid Package 4 – Field House

    • ✅DESIGN PHASE UNDERWAY - Bid Package 4 – Natatorium

  • ✅Owner Direct – SOURCING MATERIALS: Summer 2026


2027

  • Summer 2027

    • Bid Package 3 – MS Upgrade Domestic Water Heaters

    • Bid Package 3 – MS Replace Fire Alarm System

    • Bid Package 3 – MS Replace Building Temperature Controls

    • Bid Package 3 – MS Replace Chiller & Associated Pumps

    • Bid Package 3 – MS Replace Boiler & Associated Pumps

    • Bid Package 3 – MS Add 3rd Boiler for Redundancy

    • Bid Package 3 – MS Classroom Wing Security Doors

    • Bid Package 6 – Upgrade Domestic Water Heaters

    • Bid Package 6 – Upgrade ECEC Gym AHUs to Include Cooling

  • March – August 2027

    • Bid Package 4 – Tennis Court Facility

  • June 2026 – August 2027 (overlapping start)

    • DESIGN PHASE - Bid Package 3 – MS Cafeteria Renovation

  • Sept 2027 – March 2028

    • Bid Package 6 – HS Weight Room Addition


2028

  • March – August 2028

    • Bid Package 6 – HS Locker Room Renovation

  • June 2026 – August 2028 (overlapping start)

    • DESIGN PHASE - Bid Package 3 – MS Front Office Expansion

  • Summer 2028

    • Bid Package 5 – MS Replace Interior Lighting to LED

    • Bid Package 5 – MS Replace Ceiling Tiles (with Lighting Replacement)

    • Bid Package 5 – MS Replace Corridor Lockers

    • Bid Package 5 – MS Renovate Science Labs (6th & 7th Grade)

    • Bid Package 5 – MS Renovate Toilet Rooms

    • Bid Package 6 – HS Auditorium Exterior Upgrades

    • Bid Package 6 – HS Exterior Masonry Upgrades (@Entry Canopies)

    • Bid Package 6 – HS Replace Interior Lighting to LED

    • Bid Package 6 – HS Renovate Toilet Rooms

    • Bid Package 6 – HS Renovate Science Labs

    • Bid Package 6 – HS Replace Building Temperature Controls

    • Bid Package 7 – Practice Fields

    • Bid Package 7 – Baseball & Softball Upgrades

  • March – August 2028

    • TBD – Multipurpose/Soccer Competition Field


TBD

  • Owner Direct – Replace Security Cameras

  • Owner Direct – Technology District Wide: Classroom Upgrades

  • Owner Direct – Technology District Wide: Large Spaces (Gymnasium A/V)

  • Bid Package 7 – Football Stadium: Outer Scope / Entry

  • Additional bus purchasing

Additional Information at your Fingertips Additional Information at your Fingertips

User uploaded image
zoom_out_map

Supporting Docments

Click on the buttons below to review salient information

Bond 2024 Website
General Bond 2024 Information
User uploaded image
zoom_out_map

Construction

User uploaded image
zoom_out_map

Architect

User uploaded image
zoom_out_map

Owner's Representative

User uploaded image
zoom_out_map

Interior View of North Side of Building

User uploaded image
zoom_out_map

Exterior Wall Framing at Administrative Area

User uploaded image
zoom_out_map

Trim Out of Overhead Door Openings

Mattawan Consolidated School
R. Fleenor is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter