Design Input to the Modernization Project

Please click on the survey links below to give input into the interior color scheme and design concept for the new "K" quad!

English Survey
Spanish Survey
zoom_out_map

Construction Activity

  • Underground Utilities located and marked, trench excavated. Conduit, back fill, and grading.
  • Roof conduit materials staged and installed on building 300.
  • Rough plumbing and rough framing done.
  • Service area asphalt and sidewalk concrete demoed and removed.
Project Website
zoom_out_map

Saw Cutting

Preparation for trenching along Cutting

zoom_out_map
zoom_out_map

Accessibility Upgrades

Layout and Saw Cutting Behind the Cafeteria