April 17, 2025 Bond Update

November 3rd, 2023

April  17, 2025 Bond Update November 3rd, 2023
April 17, 2025 BondUpdateNovember 3rd, 2023

TECHNOLOGY REPLACEMENT UNDERWAY TECHNOLOGY REPLACEMENT UNDERWAY

Student Devices Replaced Under 2024 Bond πŸ’» Student Devices Replaced Under 2024 Bond πŸ’»

Students working on laptops
Students working on laptops
zoom_out_map

2,600 Devices set to be Replaced!

The District aims to maintain technology resources in good condition through regular replacement, reducing repair costs, and ensuring effective use by staff and students.


Thanks to the 2024 Bond, funds are available to continue this technology refresh. During the Pandemic, a large purchase of Chromebooks was made for the launch of the One-to-One program. Due to limited availability at the time, the District acquired a model already partway through its production cycle, resulting in a shorter lifespan.


Chromebooks have proven to be effective, affordable, and easy to maintain, especially for student learning and testing at the High School and Middle School levels. As the current devices approach end-of-life, the District recommends replacing them.


Through the State-Wide SPOT program, a proposal has been made to purchase 2,666 Chromebooks and management licenses at a total cost of $664,082.08.


We are so grateful to the community for its support of this bond initiative, enabling the District to put the very best technology in the hands of our learners! πŸ’•πŸ–₯οΈπŸ–²οΈβŒ¨οΈ

Laptop

Audio/Visual Equipment Replacement 🎀 Audio/Visual Equipment Replacement 🎀

Microphone with lightening shooting out of it
zoom_out_map

Middle School Gymnasium Upgrade!

As part of the 2024 Bond project, the District plans to upgrade the audio-visual systems in the Middle School gyms. The β€œOld” Gym’s outdated and unreliable controls need replacement, while the β€œNew” Gym currently lacks any AV systems.


After a competitive bidding process involving three vendors at a pre-bid walk-through, two bids were received. This project will invest about $49,993 into the middle school gymnasium AV equipment.


Installation will take place over the summer, with the systems ready for use in the 2025–2026 school year.

HVAC Controls to be Replaced πŸƒ HVAC Controls to be Replaced πŸƒ

HVAC schematic
zoom_out_map

Middle School is First up for Enhancements!

We are planning to move forward this summer with updating the HVAC controls at the middle school, which are currently outdated and no longer functioning efficiently. These controls manage the heating, ventilation, and air conditioning systems throughout the building and play a critical role in maintaining a comfortable and healthy learning environment for both students and staff.


The current control system is antiquated and has become increasingly ineffective at regulating temperatures and ensuring consistent airflow. In many cases, these older systems lack the ability to be remotely monitored or adjusted, which limits our ability to respond quickly to issues and optimize energy use. As a result, the building experiences inconsistent heating and cooling, energy inefficiency, and a greater risk of mechanical strain on the HVAC units themselves.


Upgrading to a modern, automated control system will allow for better zone control, real-time monitoring, and improved energy management. It will also extend the life of our HVAC equipment by ensuring systems are running as intended and not being overworked due to poor control responsiveness. This upgrade will represent a significant improvement in both operational efficiency and comfort for our middle school community!

Up for a Magic Carpet Ride? πŸ’« Up for a Magic Carpet Ride? πŸ’«

Carpet being installed
zoom_out_map

New Carpet Coming to the High School!

This summer, the district aims to complete a comprehensive carpet replacement project focused primarily on the Middle and High Schools. The project will target approximately 35 classrooms in the High Schoolβ€”around 14 on the first floor and 20 on the secondβ€”along with several additional spaces, including athletics offices, small storage rooms, and the tech area.


While the current plan is to complete the work before the start of the new school year, it’s worth noting that lead times on carpet materials may present some logistical challenges. Nonetheless, the summer completion timeline remains the official goal for the project.


Artist rendering, right

Partial, tentative replace maps below.

Floorplan at high school
Floorplan at high school

Furniture Overhaul Planning Underway πŸͺ‘ Furniture Overhaul Planning Underway πŸͺ‘

zoom_out_map

Middle & High Schools to Receive Updated Furniture

Planning for the replacement of student and teacher furniture in both the middle and high schools is well underway, funded by the school construction bond. To ensure the best selection, teams have visited multiple industry-leading furniture suppliers, touring showcase rooms to evaluate modern, functional options that will enhance the learning environment. Several debrief meetings have taken place to discuss findings and narrow down potential suppliers. The next step in the process will involve selected suppliers presenting their equipment for building staff and staff to pilot this fall and provide feedback on. Much of the existing furniture is over 25 years old, and the new selections will usher in updated, modern environments for both students and staff, fostering a more comfortable and engaging learning experience.

STADIUM WORK, BID PACKAGE 1A STADIUM WORK, BID PACKAGE 1A

zoom_out_map

Week 4 Stadium Work Phase 1

Week 4 saw continued momentum on-site with several key activities progressing steadily. Soil testing and approvals remained ongoing to ensure the suitability of skate park dirt for field fill, which also continued throughout the week. Tree removal efforts were actively underway along the southern border of the site. In addition, demolition work began at the Bus Garage to prepare the area for future detention pond construction. The project remains on schedule as site preparation activities continue to advance.

zoom_out_map

Stadium Aerial View

zoom_out_map

Stadium Arial View

zoom_out_map

Southwestern Tree line

zoom_out_map

Monitoring Post-Rain

zoom_out_map

Stadium

zoom_out_map

Area North of ECEC after Rain

Week 5 Stadium Work Phase 1

During Week 5, significant progress was made across multiple areas of the project. Field fill operations advanced to 80% completion, contributing to the site’s overall stabilization. The removal of soils from the former skate park also reached 80% completion, maintaining alignment with the project timeline. Excavation for the detention pond is underway, with 25% of the work completed. Additionally, all scheduled tree removal activities have been finalized, marking 100% completion in that area. Overall, the site is progressing well and remains on track with scheduled milestones.

zoom_out_map

Transportation Area Detention Pond Cut

zoom_out_map

Areas North of ECEC Cut and Base Extraction

zoom_out_map

80% Base Completion at Stadium

SITE WANDERINGS SITE WANDERINGS

Construction Site Wanderings #1

Stadium Conceptual Design Stadium Conceptual Design

Site Rendering

Stadium Construction Phases Stadium Construction Phases

zoom_out_map

Stadium Work, Phase 2 Summer 2026

It is important to note that the stadium will be renovated in multiple phases. Phase two, scheduled to begin in the Summer of 2026 and will include renovations to the current press box and the addition of a new sound system.

Stadium Work, Phase 3

Phase three will include the construction of a new entryway and concession on the south end of the current stadium, as well as cosmetic improvement the current entry way on the North side of the stadium.

BID PACKAGE 2A PLANNING UNDERWAY BID PACKAGE 2A PLANNING UNDERWAY

zoom_out_map

Bold Designs for New Maintenance and Transportation Complex

Exciting progress is underway as we move forward with the design of a new Transportation and Maintenance Building, set to begin construction this fall! Located just west of the current high school, this much-needed facility will replace outdated and undersized buildings that no longer meet modern safety standards.


Designed for efficiency, this 24,000-square-foot building will combine both departments, maximizing resources and making the best use of taxpayer dollars. It will include administrative offices, locker and shower facilities, and dedicated garage space for both transportation and maintenance teams. With four drive-through bays, our talented team of mechanics can now service buses more safely and efficiently, eliminating the need for backing in or out.


This new facility will also provide additional dry storage with a dock, streamlining district-wide deliveries and distribution. This investment ensures our district operates more effectively while supporting the vital work of our transportation and maintenance staff.

2024 SCHOOL CONSTRUCITON BOND POLL 2024 SCHOOL CONSTRUCITON BOND POLL

What external item are you looking forward to the most?

date_range Voting ends in 8 days
remove_red_eye Votes are anonymous and results are private
Loading...

ARCHIVED INFORMATION ARCHIVED INFORMATION

Construction Bid Packages Explained Construction Bid Packages Explained

zoom_out_map

Construction Bid Packages Exlplained

The work captured in this bond is broken down into bid packages. For example, the work described above is in Bid Package 1A - the very first bid package. Upcoming bid packages are outlined below with tentative timelines.


Please note: The bid packages listed below are currently in various stages of design. Additional bid packages, including those for field turf, the middle school cafeteria, technology, the natatorium, and others, have not yet entered the design phase but will be developed and updated in the future.


Bid Package 1A - Stadium Inner Scope

  • Replace field with turf
  • Replace track & field
  • Replace inner perimeter fencing
  • Fall 2024 - project design
  • Winter 2024 - projects bidding
  • Spring 2025 - project construction


Bid Package 1B - Campus Traffic Flow & Parking

  • High School and Middle School parent carpool loop reworked
  • Separation of buses from carpool/community traffic
  • Expanded parking in front of middle and high school
  • Stadium press box renovations
  • Spring 2026 - projects bidding
  • Summer of 2026 - project construction


Bid Package 1C - Baseball & Softball Field Upgrades

  • Update irrigation system
  • Updated perimeter fencing
  • Spring 2025 - project bidding
  • Summer 2025 - construction


Bid Package 1D - Middle/High School Fire Alarm System Replacement

  • Winter 2025 - project bidding
  • Summer 2025 - construction


Bid Package 2A - New Construction Transportation & Maintenance Facility

  • Winter 2025 - Design Development
  • Summer 2025 - project bidding
  • Fall 2025 - Fall of 2026 - construction

Our Plan. Our Students. Our Future. Our Plan. Our Students. Our Future.

zoom_out_map

Our focus revolves around five key objectives for the bond:


  1. Preserve existing assets
  2. Prioritize safety and security
  3. Provide future-focused academic and extracurricular experiences for our students
  4. Enhance infrastructure
  5. Demonstrate fiscal responsibility


Safety & Security:

  • Addressing traffic congestion, lack of parking spaces, and separation of traffic and busing through enhancements
  • Replacement of outdated, unreliable security equipment at each building

Transportation:

  • Continued replacement of an aging bus fleet

Academic Learning Spaces + Experience:

  • Replacement of original, aged classroom equipment and furniture at middle and high schools
  • Updates to original, outdated science areas at middle and high schools (excluding the newly renovated portions) to ensure students have state of the art experiences.

Fine Arts:

  • Upgrades to lighting and media equipment at the high school auditorium

Infrastructure:

  • Replacement of original, outdated lockers, bathrooms, various ceilings, and lighting at middle and high schools
  • Renovations to high school weight room including expansion to address overcrowding and scheduling issues for student-athletes and physical education courses
  • Upgrade of aged building controls at middle and high schools (water, fire, HVAC, etc.) to provide the most efficient and safe environmental controls
  • Addition of cooling to main gymnasiums at the high school

Student Athletic Experience:

  • Renovation of aged high school locker rooms
  • Renovation of the high school stadium, including artificial turf, new entryways, expanded concessions
  • New high school track - the current track is backwards and nearly unusable in the current condition
  • Upgrades to baseball and softball fields
  • Construction of a new multi-use turf field (soccer, lacrosse, football)
  • Maintenance of existing practice fields; addition of a new outdoor practice space

Other Construction:

  • Addressing overcrowding in the current Middle School cafeteria
  • Replacement of aged, quickly deteriorating tennis courts
  • Replacement of aged transportation building and maintenance building
  • Construction of a fieldhouse facility for indoor practice teams/band to address lack of 12-month practice space; available for community use
  • Construction of a student/community pool

Additional Information at your Fingertips Additional Information at your Fingertips

zoom_out_map

Supporting Docments

Click on the buttons below to review salient information

Bond 2024 Website
General Bond 2024 Information
zoom_out_map

Construction

zoom_out_map

Architech

zoom_out_map

Owner's Representative

Mattawan Consolidated School
R. Fleenor is using Smore to create beautiful newsletters
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter