Montclair Public Schools
September 16, 2024
Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE
District Wide Boiler Replacement
Replacement of aged boilers, feeder tanks, and electrical components as required
Awarded Contract Amount: $3,785,100.00 - This is for all boiler replacements
Paid to Date: $3,339,057.00
Renaissance @ Rand
Project Status: May 8, 2026
Project Completion: 93% complete
Current Status: Insulation is being completed; draft controls installed; boiler #2 start up; painting being completed
Upcoming Milestones: Feed unit tie-in to be completed
George Inness
Project Status: May 8, 2026
Project Completion: 95% complete
Current Status: Preparing to replace sump pump
Upcoming Milestones: Punchlist and closeout
Bradford Elementary
Project Status: May 8, 2026
Project Completion: 94% complete
Current Status: Feed Unit is in place and start up is complete
Upcoming Milestones: Boiler #2 boil out; preparing to complete sump pit repairs
Watchung Elementary
Project Status: May 8, 2026
Project Completion: 95% complete
Current Status: Repairing existing sump pit
Upcoming Milestones: Punchlist and closeout
Edgemont Elementary
Project Status: May 8, 2026
Project Completion: 93% complete
Current Status: Boiler #2 start up
Upcoming Milestones: Complete feed unit tie-in 100%
Northeast Elementary
Project Status: May 8, 2026
Project Completion: 92% complete
Current Status: Painting being completed
Upcoming Milestones: Feed unit piping and wiring to be completed