Montclair Public Schools

September 16, 2024

Montclair Public Schools  September 16, 2024
MontclairPublic Schools September 16, 2024

Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE Boiler Replacement: Rand, Bradford, Inness, Edgemont, NE

District Wide Boiler Replacement

Replacement of aged boilers, feeder tanks, and electrical components as required

Awarded Contract Amount: $3,785,100.00 - This is for all boiler replacements
Paid to Date: $3,339,057.00

Renaissance @ Rand Renaissance @ Rand

Project Status: May 8, 2026

Project Completion: 93% complete

Current Status: Insulation is being completed; draft controls installed; boiler #2 start up; painting being completed

Upcoming Milestones: Feed unit tie-in to be completed

User uploaded image
zoom_out_map Show in original size

George Inness George Inness

Project Status: May 8, 2026

Project Completion: 95% complete

Current Status: Preparing to replace sump pump

Upcoming Milestones: Punchlist and closeout

User uploaded image
zoom_out_map Show in original size

Bradford Elementary Bradford Elementary

Project Status: May 8, 2026

Project Completion: 94% complete

Current Status: Feed Unit is in place and start up is complete

Upcoming Milestones: Boiler #2 boil out; preparing to complete sump pit repairs

User uploaded image
zoom_out_map Show in original size

Watchung Elementary Watchung Elementary

Project Status: May 8, 2026

Project Completion: 95% complete

Current Status: Repairing existing sump pit

Upcoming Milestones: Punchlist and closeout

User uploaded image
zoom_out_map Show in original size

Edgemont Elementary Edgemont Elementary

Project Status: May 8, 2026

Project Completion: 93% complete

Current Status: Boiler #2 start up

Upcoming Milestones: Complete feed unit tie-in 100%

User uploaded image
zoom_out_map Show in original size

Northeast Elementary Northeast Elementary

Project Status: May 8, 2026

Project Completion: 92% complete

Current Status: Painting being completed

Upcoming Milestones: Feed unit piping and wiring to be completed

User uploaded image
zoom_out_map Show in original size

Newsletters Updates

November of 2022, in a historic show of unity, more than 80% of town voters backed the $188 million Bond Referendum to repair and modernize Montclair Public Schools' long-neglected buildings and decaying infrastructure (11 schools and the administration building constructed more than 99 years ago on average).

launch montclair.k12.nj.us
User uploaded image
zoom_out_map Show in original size
Conor O'Brien- Principal
Legacy Construction Management
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter