Collins ES Critical Needs Project

September 2023

Collins ES Critical Needs Project September 2023
Collins ES Critical Needs Project September 2023

Project Updates - September 2023 Project Updates - September 2023

zoom_out_map

Construction Completed Last Month

  • Continued installation of the refrigerant piping on the classroom hallway roofs.
  • Installations of condensing units in the outdoor equipment enclosures

Upcoming Activities

  • Complete piping on the classroom hallway roofs
  • Complete "Cougar Pride" striping and landscaping restoration at the student drop-off
  • Look for the next project newsletter in Winter 2023 / Spring of 2024 when the new electrical equipment is delivered, which will allow for the completion of this project.

Project Overview Project Overview

  • Project Scope: Improvements to site HVAC Systems, Electrical Infrastructure, and Accessibility including path of travel improvements and parking lot updates.
  • Architect: PBK Architects

  • Anticipated Completion: Spring 2024

Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
zoom_out_map

Shrouded piping on hallway roofs

zoom_out_map
zoom_out_map

New classroom door hardware

Collins Critical Need Project Newsletter
WCCUSD Facilities Planning & Construction
Signature facebook Signature instagram
Loading indicator

close

Created with

Communicate quickly and effectively with interactive newsletters.

Smore empowers educators to connect with their community, streamline school communications,
and increase engagement.

Create a newsletter